In brief
The sale and purchase agreement (SPA) with a developer in Dubai is usually drafted by the developer, and it determines most of your rights beyond the statutory minimum. Before signing it is advisable to check at least 12 clauses: the identity of the parties and the project, the description of the unit and its area, the specification, the payment plan and the Escrow account, the completion date and extensions, delay and compensation, default and termination, Oqood registration and fees, assignment and sale before handover, service charges, handover and defects, and governing law and jurisdiction. Some of the topics are regulated by Dubai law in a way that the contract cannot derogate from, and in others the contract is all there is.
Key takeaways
- 1Some protections are enshrined in law and prevail over the contract: an area smaller by more than 5% entitles the buyer to compensation, and the retention rates on buyer default are caps that are public policy.
- 2The payment plan should be linked to construction milestones, and the payments should reach the project's Escrow account.
- 3The completion date clause, the extension period and force majeure determine in practice your rights in the event of delay.
- 4A material deviation from the agreed specification is a ground to ask the court to rescind the contract (Article 20 of Resolution 6/2010).
- 5A dispute over a property in Mainland Dubai will not be heard in the DIFC Courts even if the contract so provides, so it is important to understand what the jurisdiction clause actually allows.
Many Israeli buyers receive the Sale and Purchase Agreement (SPA) only after they have paid a down payment, and sometimes as a long file in English that must be signed within days. That is exactly the stage at which it is worth stopping. The SPA with a developer in Dubai is a contract drafted by the developer, and it defines what you will receive, when, and what happens if something goes wrong. This guide goes through 12 clauses worth checking, and distinguishes between what Dubai law guarantees in any event and what depends solely on the wording of the contract.
What is an SPA in Dubai and how does it relate to the law?
The SPA is the contract between the buyer and the developer for a particular unit in the project. In an Off-plan purchase it is registered in the DLD's interim register (Oqood) under Dubai Law 13/2008, and a transaction not registered there is void (Article 3). Alongside the contract, the escrow law 8/2007, the regulations to Law 13/2008 (Executive Council Resolution 6/2010), the jointly owned property law 6/2019 and the federal Civil Code apply. The developer's standard sale contract is one of the documents the developer submits in order to open an Escrow account for the project (Article 6 of Law 8/2007).
Even when the developer says the contract is standard and not open to negotiation, the review is essential: it shows you the risks you are taking, and sometimes it is possible to obtain a clarification letter or an addendum that changes an important point.
The 12 clauses worth checking in a Dubai SPA

1. Who are the parties and what is the project?
Check that the selling party is the project's developer as registered with the DLD, and not another company in the group or a marketer. Check that the project number and plot number in the contract match the registration. If you are buying together with a spouse or partner, check how each of you is registered and in what share. If the purchase is through a company, it is important to know that a company with a foreign shareholder is restricted to areas designated for foreigners, like a foreign individual.
2. Description of the unit, the area and the floor plan
The area in the contract is the basis for any future claim. The regulations provide that the net area in the contract and the plan is the basis of calculation, that additional area is not paid for unless otherwise agreed, and that if the actual area is smaller by more than 5% of the net area, the developer must compensate the buyer according to the agreed unit price (Article 13 of Resolution 6/2010; Article 12 of Law 13/2008). Check that the contract defines a net area, that the unit plan is attached as an annex, and that it states whether parking or storage is included. What happens when the apartment differs from what was presented is explained in the guide to an apartment that differs from the specification.
3. The specification, the materials and the developer's right to change
Check whether there is a binding specification annex or only a reference to marketing materials. Also check whether the contract allows the developer to replace materials or change the design, and on what conditions. The regulations allow the buyer to ask the court to rescind the contract when the developer materially deviates from the agreed specification (Article 20(3) of Resolution 6/2010), but the question of what was agreed will be decided according to the contract and its annexes. What is not written in the contract is very hard to prove.
4. The price, the payment plan and the Escrow account
Check three things: that the payments are linked to construction milestones and not only to dates, that all payments are directed to the project's Escrow account, and what happens to payments after handover. The regulations allow the buyer to ask the court to rescind the contract when the developer refuses to link the payments to the milestones proposed by RERA (Article 20(2) of Resolution 6/2010). A payment plan extending beyond handover raises separate questions, which are explained in the guide to payment plans and Post Handover.
5. The completion date, the extension period and force majeure
This is one of the most important clauses. According to a review by a Dubai law firm, many contracts set an anticipated completion date and allow the developer to extend it by a further 12 months, and in addition exempt certain delays as force majeure events. Check what is defined as force majeure, whether there is a notice requirement, and whether there is a final date after which you may terminate. The regulations list reasons considered beyond the developer's control, including expropriation, government suspension for replanning and changes at the master developer (Article 21 of Resolution 6/2010).
6. Compensation for late handover
We did not find in Dubai law fixed and automatic compensation for late handover. What determines it is the contract, and sometimes the court under the general law. Check whether the contract has agreed compensation, from what date it begins, whether it has a cap, and whether you have a right to terminate and get the money back after a certain delay. The default in the absence of such a clause is legal proceedings. See also the guide to delayed handover.
7. What happens if you do not pay on time?
Here the law sets a framework that the contract cannot make stricter. Under Article 11 of Law 13/2008 as worded by Law 19/2020, after the developer's notice, the DLD gives the buyer a 30-day notice and tries to mediate. If the default is not remedied, the developer's rights depend on the percentage of completion:
| Percentage of completion | What the developer may do |
|---|---|
| Above 80% | Keep the contract and claim the balance, ask the DLD for a public auction of the unit, or terminate and retain up to 40% of the unit's value |
| 60%-80% | Terminate and retain up to 40% of the unit's value |
| Below 60% (works have begun) | Terminate and retain up to 25% of the unit's value |
| Construction has not begun for reasons beyond the developer's control, or cancellation by RERA decision | Refund of all the funds under Law 8/2007 |
The surplus is returned within one year of termination or within 60 days of the resale of the unit, whichever is earlier. The rules are public policy, so a contract clause allowing the developer more than this is not valid. Also check the late-payment interest and default fees set by the contract. On the situation in which it is difficult to make a payment see the guide to payment default in Off-plan.
8. Oqood registration and who pays the fees
Check who is responsible for registering the transaction in the interim register and who pays the fees. Under the regulations, unless otherwise agreed, each party pays its share of the registration fees (Article 9 of Resolution 6/2010), and in practice contracts usually place most of the fees on the buyer. In a resale transaction the DLD transfer fee is 4% of the transaction value, as of November 2026; for Oqood registration secondary sources cite a similar rate. The regulations also prohibit a developer from collecting from the buyer an amount not approved by the DLD (Article 8 of Resolution 6/2010).
9. Assignment and sale before handover
According to the DLD, an Off-plan unit can be sold before its transfer to the permanent register, but only with a No Objection Certificate (NOC) from the developer. Check whether the contract makes assignment conditional on payment of a certain percentage of the price, and what fee the developer charges. Law 13/2008 prohibits a developer from charging fees on a sale or other transaction in the unit, other than administrative costs approved by the DLD (Article 7). See the guide to selling Off-plan rights.
10. Service Charges
Check from what date you will begin paying service charges and whether there is an initial estimate. Under Law 6/2019, service charges may not be collected before RERA has approved the budget. The Rental Disputes Center held in 2025 that a buyer registered in the interim register is liable for service charges from the date of completion of the project, even before ownership has been transferred to them. The approved service charges per project can be checked in the DLD service charge index.
11. Handover, snagging inspection and liability for defects
Check what must happen before handover is considered complete, whether you have a right to a defects inspection before receiving the keys, and how reservations are documented. Under Law 6/2019 (Article 40), the developer is responsible for repairing defects in the structure of the common property for 10 years from the completion certificate, and defective installations for one year. The regulations provide that after the completion certificate the developer may not refuse to hand over a unit to a buyer who has met its obligations (Article 7 of Resolution 6/2010). Full details are in the guide to taking possession and snagging inspection in Dubai.
12. Governing law, jurisdiction and arbitration
Many contracts refer to arbitration, and according to a review by a Dubai law firm this is the most common method of dispute resolution in SPAs. Since 2021 the main arbitration institution in Dubai has been DIAC. If there is no arbitration clause, the dispute will be heard in the Dubai courts, in Arabic, with a certified translation of the documents. It is important to know: the DIFC Small Claims Tribunal held (Hackett v Hania, 2017) that it has no jurisdiction over a claim concerning a property in Mainland Dubai, even where the parties agreed to its jurisdiction. On the differences between the forums see the guide to the DIFC Courts versus the onshore courts.
What is the Israeli side of reviewing the SPA?
Three things are important for an Israeli buyer: the contract is denominated in dirhams, so every payment is exposed to the shekel exchange rate; the bank in Israel will usually ask to see the contract and the source of funds before a transfer; and remote signing through an attorney-in-fact requires an authentication chain, because the UAE is not a party to the Apostille Convention, so authentication is required at the Israeli Ministry of Foreign Affairs, at the UAE Embassy in Tel Aviv and as needed at the UAE Ministry of Foreign Affairs, with a legal translation into Arabic. On the currency clause see the guide to a currency clause in a property contract abroad.
Before you sign: how we assist
We read the SPA before any payment, mark the clauses in which the contract departs from what is customary or from the law, and draft for the client a short list of what to request from the developer in writing. The review against Dubai law and the authorities there is carried out in coordination with locally licensed lawyers. We handle the remote signing documents, the authentications and the Israeli side of the transaction from here.
The information in this article is general and current as of November 2026, and does not constitute legal advice on a particular contract. Every SPA is different, and the outcome of a dispute depends on the exact wording and the circumstances. The specific contract should be reviewed with a lawyer before signing.
Frequently asked questions
Can a Dubai developer's SPA be negotiated?
The developer often presents the contract as standard. Even then it is sometimes possible to obtain a clarification letter or an addendum on points such as the completion date, parking or the payment plan. Even when there is no change, the review shows you exactly which risks you are taking.
What happens if the area I received is smaller than the area in the contract?
Under the regulations to Law 13/2008, if the actual area is smaller by more than 5% of the net area in the contract, the developer must compensate according to the agreed unit price. If the area is larger, the developer may not demand an additional payment, unless otherwise agreed.
Can a developer keep all the money if I stopped paying?
Not in every case. Article 11 of Law 13/2008 as worded by 19/2020 sets caps: up to 40% of the unit's value when the project is more than 60% complete, and up to 25% below 60% when works have begun. Above 80% the developer may also keep the contract and claim the balance or request a public auction. The rules are public policy.
Is there fixed statutory compensation for late handover in Dubai?
We did not find fixed statutory compensation. The rights are determined by the contract, including the extension period and force majeure, and sometimes by the court. So the completion date and compensation clause is one of the most important to check.
Should the SPA provide for the jurisdiction of the DIFC Courts?
As regards a property in Mainland Dubai, the DIFC Courts have held that they have no jurisdiction even when the parties agreed to it. So such a clause will not necessarily help. It is more important to understand whether the contract refers to arbitration, where, and in which language.
Can you sign an SPA in Dubai from Israel?
Yes, usually by electronic signature or through an attorney-in-fact. A power of attorney signed in Israel requires an authentication chain, because the UAE is not a party to the Apostille Convention, and usually also a legal translation into Arabic.
When do you start paying service charges?
According to a 2025 ruling of the Rental Disputes Center, a buyer registered in the interim register is liable for service charges from the date of completion of the project, even before transfer of ownership. Service charges require RERA approval, and the approved amounts can be checked in the DLD index.
What is the difference between a reservation agreement and an SPA?
A reservation agreement is signed before the SPA and is usually accompanied by a down payment, sometimes 5%-10% according to a review by a Dubai law firm. The SPA is the full contract. It is advisable to see the wording of the SPA before paying a down payment.
Read next · 13 min readMy Dubai Apartment Differs from the Specification: Your Rights When the Area, View or Finishes Do Not MatchDubai unit differs from the spec: when a shortfall over 5% is compensated, what to do about finishes or view, how to document before handover, and your options.Read the guideSources
- Dubai Legislation Portal - Executive Council Resolution No. (6) of 2010
- Dubai Legislation Portal - Law No. (19) of 2020 Amending Law No. (13) of 2008
- Dubai Legislation Portal - Law No. (13) of 2008
- Dubai Land Department - Frequently Asked Questions
- DIFC Courts - Hackett v Hania [2017] DIFC SCT 034
- Afridi & Angell - Off-plan construction delays: options for resolution in Dubai
- Dubai Rental Disputes Center - new legal principle on real estate service fees