In brief
A delay in the handover of an Off-plan apartment in Dubai does not cancel the transaction by itself. The buyer's rights are determined first and foremost by the sale contract (SPA), in particular the anticipated completion date, the grace period and the compensation clause, and in parallel the funds are supposed to sit in an Escrow account dedicated to the project under Law 8 of 2007. Where the delay is serious, you can apply to the regulator (RERA), sue for cancellation and compensation in the Dubai courts or in arbitration under the contract, and if RERA cancels the project, the law requires the developer to refund all the money. The most expensive mistake is to stop paying without advice, because then it is the buyer who is in breach, and the developer may invoke Article 11 against them.
Key takeaways
- 1A delay does not give an automatic right to stop paying. A buyer who stops paying is exposed to termination under Article 11 of Law 13/2008, as amended by Law 19/2020, and to the developer retaining up to 25% or 40% of the unit's value.
- 2The money you paid is supposed to be in a separate Escrow account for the project, and the developer's creditors cannot attach it (Article 9 of Law 8/2007).
- 3If RERA cancels the project by a final, reasoned decision, the developer must refund all payments (Article 11(b) of Law 13/2008 as amended).
- 4A project where construction started and stopped is an "unfinished project", and disputes concerning it are heard by the Special Tribunal under Decree 33 of 2020, not by the ordinary courts and not in the DIFC.
- 5In a judgment reported in 2026, a Dubai court reduced what the developer may retain from 40% to 10% because of a prolonged delay. This is an example, not a rule.
You bought an apartment off-plan in Dubai, the handover date has passed or is about to pass, and the developer is sending notices of a "schedule update". This is one of the most common and stressful situations for an Off-plan buyer, especially for an Israeli buyer who is not on the ground. This guide explains what Dubai law actually gives the buyer, what it does not give, how to distinguish between an ordinary delay and a stalled project, and what the correct order of steps is, so that you do not turn from the injured party into the party in breach.
The short answer
A delayed handover is first and foremost a contractual question: what the SPA says about the anticipated completion date, the grace period and compensation. If the delay goes beyond the contract, you can claim compensation or termination in the Dubai courts or in arbitration, and if RERA cancels the project, the law requires a full refund of the payments. What you must not do is stop paying on your own initiative, because then the developer can terminate the contract and retain a significant part of the money.
Why are handovers delayed in Dubai and what does it mean legally?
Most delays stem from the pace of construction, financing, contractors or approvals, and the contract usually anticipates them. In the SPA of many projects, the handover date is phrased as an "anticipated completion date", alongside a right of the developer to extend it by an additional period, and sometimes also a broad force majeure clause. According to a review by Afridi & Angell, developers not infrequently claim a right to an additional 12-month extension or force majeure, so before any step these clauses must be read precisely.
The practical meaning: not every delay relative to the date stated at the project presentation is a breach. A breach begins only when the developer goes beyond the contractual date and the grace period, or when construction actually stops. This distinction also determines both the forum and the remedy.

What does Dubai law say about a developer's delay?
There is no single statutory provision in Dubai setting "compensation of X for each month of delay". The buyer's protection is built from several layers: registration of the transaction, an Escrow account, RERA supervision, a project cancellation track, and the general law of contracts. The table summarises what each layer provides.
| Law or body | What it provides | What it gives a buyer facing delay |
|---|---|---|
| Law 13 of 2008 (Interim Register), Article 3 | Every Off-plan sale is registered in the interim register (Oqood), and a sale that was not registered is void | Official proof of your right to the unit, not dependent on the developer's records |
| Law 8 of 2007 (Escrow), Article 9 | A separate Escrow account for each project; the funds are designated only for its construction and cannot be attached for the developer's debts | The money you paid should not fund other projects or serve creditors |
| Law 8 of 2007, Article 15 | Where a project will not be completed due to emergency circumstances, the Escrow agent consults with the DLD and acts towards completion or refund to the depositors | A statutory mechanism for completion or refund, not just a personal claim |
| Article 11(b) of Law 13/2008, as worded by Law 19/2020 | Construction that did not start for reasons beyond the developer's control, or a project RERA cancelled by a final, reasoned decision: the developer refunds all payments | A 100% refund in the event of official cancellation |
| Decree 33 of 2020 | A Special Tribunal for unfinished and cancelled projects, with exclusive jurisdiction | A forum that can order the Escrow agent to refund money or transfer the project to another developer |
| General contract law | A contract is performed according to its content and in good faith; a new Civil Code (Federal Decree-Law 25/2025) in force from 1.6.2026 | A basis for a claim for compensation or termination for breach |
It is important to understand Article 11 correctly, because there is much confusion around it. The Article, as worded by Law 19 of 2020 (signed on 24.11.2020 and in force on the date of its publication), deals with a situation in which the buyer is in breach, for example has stopped paying. It does not give the buyer a remedy for the developer's delay. It does provide that where RERA cancels a project, the developer must refund all the money in accordance with Law 8 of 2007, and that the buyer retains the right to go to court or arbitration (Article 11(g)). The rules are defined as part of public order, and any action contrary to them is void.
Many websites still state that a developer may retain up to 30% of payments when construction has not started. That was the wording of Law 9 of 2009 and of Law 19 of 2017. Law 19 of 2020 replaced it, and today, where construction has not started for reasons beyond the developer's control and without negligence on its part, or where RERA has cancelled the project, the obligation is to refund all payments.
When does a delay become an "unfinished" or "cancelled" project?
The distinction between the three situations determines where you turn. A project progressing slowly is an ordinary contractual matter. A project where construction started and stopped is defined in Decree 33 of 2020 as an "unfinished project". A project that RERA cancelled by a final, reasoned decision is a "cancelled project", and there is also an intermediate stage of review towards cancellation.
| Project status | What characterises it | Main forum | Expected remedy |
|---|---|---|---|
| Delay within the contract | The anticipated date has passed, but the developer is within the grace period, and construction continues | No cause of action yet; monitoring and documentation | Usually no remedy at this stage |
| Delay beyond the contract | The grace period has ended, construction continues | The Dubai courts or arbitration (according to the dispute resolution clause in the SPA), after applying to RERA | Compensation under the contract and the law, and sometimes termination and refund |
| Unfinished project | Construction started and stopped | The Special Tribunal under Decree 33/2020, to which RERA refers projects | Completion, transfer to another developer, or an order to the Escrow agent |
| Cancelled project | A final, reasoned decision by RERA | The Special Tribunal under Decree 33/2020 | Full refund of payments under Article 11(b) and Law 8/2007 |
Under Article 10 of Decree 33 of 2020, the Dubai courts, including the DIFC Courts, do not accept new claims within the jurisdiction of the Special Tribunal, and pending cases are transferred to it. Under Article 11 of the Decree, its decisions are final and not subject to appeal in the ordinary way, and they are enforced through the Execution Court of the Dubai Courts. The Decree does not apply to projects within the DIFC. On the full cancellation track, see the project was cancelled: how to get the money back from the Escrow account.
Am I entitled to compensation for the delay?
Perhaps, but it depends almost entirely on the contract and the evidence. If the SPA contains an agreed compensation clause for delay, that is the starting point. If not, you can claim damages under contract law, but you must prove breach and damage, and proceedings in the Dubai courts are conducted in Arabic, on the basis of documents, and usually with a court-appointed expert.
An example from case law: according to a Gulf News report from February 2026, a buyer purchased a unit in 2017 whose handover was set for the end of 2018, with an extension until December 2019. According to RERA reports, completion in January 2019 stood at about 15%, and the project was completed only in February 2023. The buyer stopped paying, and the developer terminated the contract under Article 11 and retained the money. The court held that a prolonged delay is a serious breach by the developer, and that retaining the full 40% would be unjust, and reduced the rate to 10% of the unit's value, with interest of 5% from the date the claim was filed. The lesson is twofold: the courts weigh the delay, but the buyer still lost the apartment and had to conduct proceedings to get part of their money back.
What to do now - step by step
The order matters more than speed. This is the right way to act when the handover is delayed:
- Do not stop paying on your own initiative. As long as the contract is in force, a payment not made on time is your breach, and opens the Article 11 track for the developer.
- Gather the documents: the SPA and every annex, the Oqood registration confirmation, receipts for every payment, the details of the Escrow account you paid into, and all correspondence with the developer or the marketer.
- Read the timing clauses: anticipated completion date, grace period, definition of force majeure, compensation clause for delay, the buyer's termination rights, and the dispute resolution clause (court or arbitration).
- Check the project's status with the regulator: the completion percentage reported to RERA, and whether the project is flagged as delayed, under review towards cancellation or cancelled. This check is best carried out through a licensed local lawyer.
- Verify that the money reached the Escrow account: if you paid into another account (a general account of the developer, of a marketer or in cash), that is a separate problem that needs to be dealt with immediately.
- Send the developer a written request asking for an updated handover date, an explanation for the delay and its position on compensation, and keep the reply.
- File a complaint with RERA/DLD when there is no satisfactory answer. According to Afridi & Angell, applying to the regulator is the accepted first step, and RERA may cancel a project where the developer fails to carry it out through gross negligence.
- Decide on a track: negotiation towards a settlement (compensation, change to the payment schedule, replacement unit), a claim in court or in arbitration under the contract, or joining proceedings before the Special Tribunal if the project has been designated unfinished or cancelled.
- Coordinate the Israeli side: the effect on reporting to the Israel Tax Authority, on currency and on bringing money back to Israel if restitution is received.
Under Article 11, after the developer notifies the DLD of a breach, the buyer receives a 30-day written notice, and the DLD may mediate. These are the most important 30 days in the transaction: this is the time to remedy, settle or raise the delay arguments, not afterwards.
How to prevent it in advance
Most of the protection is determined before signing. A checklist for an Off-plan buyer:
- Check that the developer is registered with the DLD and that the project is registered and approved before the first payment. Under Article 10 of Law 13/2008, a private contract for a project that has not been approved is void. See how to check a developer in Dubai before paying.
- Pay only into the project's Escrow account, and keep confirmation of every transfer.
- Require an agreed compensation clause for delay, and limit the grace period and the definition of force majeure.
- Examine the dispute resolution clause: Dubai courts, DIAC arbitration, and what this means for language, cost and duration.
- Do not rely on dates stated at a marketing event. What counts is the SPA. See the SPA in Dubai: clauses to check before signing.
- Check the payment plan: how much is paid before completion, and whether payments are linked to construction milestones.
- Ensure Oqood registration in your name, and keep the certificate.
Common mistakes
- Stopping payments as a "protest": puts the buyer in the position of the party in breach and allows the developer to terminate and retain up to 25% or 40% of the unit's value, depending on the construction stage.
- Relying on a marketer's oral promises: the marketer is not a party to the SPA, and its undertakings do not bind the developer.
- Suing in the wrong forum: an unfinished or cancelled project belongs to the Special Tribunal, and a property in mainland Dubai will not be heard in the DIFC even by consent. This was held in Hackett v Hania (2017).
- Citing the old wording of Article 11 (30% where construction has not started), which was replaced by Law 19 of 2020.
- Waiting too long: the more time passes without documentation and a written request, the harder it is to prove the breach and the damage.
- Signing a developer's "settlement" or annex without reading it: such annexes sometimes include a waiver of past claims in exchange for a small discount.
What about the Israeli side?
A delay does not change the reporting obligations in Israel, but it affects planning: planned rental income is delayed, the payment schedule may change, and if restitution or compensation is received, the money will return to Israel and its source will need to be explained to the bank. It is worth keeping all correspondence and receipts for the Israeli bank as well. On reporting, see the Israeli side of activity abroad, and on the bank, see delayed transfers abroad and source of funds.
Before you sign / how we assist
We assist Israeli buyers in Off-plan transactions in Dubai in coordination with licensed local lawyers: we check the registration of the developer and the project and the Escrow account before the first payment, review the timing, compensation and force majeure clauses in the SPA, and when there is a delay, map the contractual and regulatory position and build the sequence of steps before anyone stops paying or sends a letter. Further reading: the risk map of buying Off-plan in Dubai and can't pay the next Off-plan instalment.
This guide is general information current as of November 2026 and is not legal advice. Every transaction and every contract is examined on its merits with a licensed local lawyer in Dubai, and the Arabic text of the legislation prevails over the English translation.
Frequently asked questions
My Dubai developer is late with handover - am I entitled to compensation?
It depends mainly on the SPA. If there is an agreed compensation clause for delay, that is the starting point. If not, you can claim compensation under contract law in the Dubai courts or in arbitration, provided the developer has gone beyond the contractual date and the grace period and damage can be proven.
Can I stop paying the developer when construction is delayed?
Not recommended without advice. Stopping payment is considered a breach by the buyer, and the developer may open proceedings under Article 11 of Law 13/2008: a 30-day notice through the DLD, followed by termination and retention of up to 25% or 40% of the unit's value, depending on the construction stage.
How long can a Dubai developer delay handover?
There is no uniform number of months in the law. What counts is the date in the SPA and the grace period set in it, and sometimes also a force majeure clause. According to a professional review, developers not infrequently claim a right to an additional 12-month extension, so the specific contract must be read.
What happens to my money if the project stalls?
Funds deposited in the project's Escrow account are designated only for its construction and are protected from attachment by the developer's creditors (Article 9 of Law 8/2007). If the project is not completed, the Escrow agent acts with the DLD towards completion or refund (Article 15), and the Special Tribunal under Decree 33/2020 can order a refund or transfer the project to another developer.
When do you get a full 100% refund?
Under Article 11(b) of Law 13/2008, as worded by Law 19/2020, when RERA cancels the project by a final, reasoned decision, or when construction has not started for reasons beyond the developer's control and without negligence on its part. In these situations the developer must refund all payments, in accordance with the procedures of Law 8/2007.
Where do you file a claim against a developer who is late?
If the project is still being built, according to the dispute resolution clause in the SPA: the Dubai courts or arbitration, for example DIAC. If the project has been designated unfinished or cancelled, jurisdiction lies with the Special Tribunal under Decree 33/2020, and the ordinary courts and the DIFC do not accept new claims on the matter.
Can I sue the developer in the DIFC Courts?
Usually not, where the property is in mainland Dubai. In Hackett v Hania (2017) it was held that the DIFC has no jurisdiction over a claim concerning property outside the DIFC even where the parties agreed to it. In addition, Decree 33/2020 excludes the jurisdiction of all courts, including the DIFC, in matters within the jurisdiction of the Special Tribunal.
What is the difference between a delayed project and a cancelled project?
A delayed project continues to be built, and the dispute is contractual. A cancelled project is one regarding which RERA has issued a final, reasoned decision, and then the full refund obligation applies. Between them is an "unfinished project", where construction started and stopped, which belongs to the Special Tribunal.
Can a Dubai court reduce what the developer retains?
According to a 2026 report, yes. A Dubai court reduced the retention from 40% to 10% of the unit's value, because the developer itself had been late for a prolonged period. This is a decision in specific circumstances and not a binding rule, and each case is examined on its merits.
Do I need to fly to Dubai to deal with the delay?
Usually not. Most steps, from checking the project's status to a complaint or a claim, can be handled through a licensed local lawyer, with a suitable power of attorney. The United Arab Emirates is not a party to the Apostille Convention, so a power of attorney from Israel requires a full chain of legalisation and translation into Arabic.
Read next · 12 min readYour Partner or Client in Dubai Has Stopped Paying - How Do You Sue? Debt Collection Routes, Arbitration and LitigationPartner or client in Dubai not paying? What to do: check the contract, demand letter, payment order, bounced cheque, DIAC arbitration, DIFC, attachment, Israel.Read the guideSources
- Dubai Legislation Portal - Law No. (19) of 2020 amending Law No. (13) of 2008 (Article 11)
- Dubai Legislation Portal - Law No. (13) of 2008 Regulating the Interim Real Property Register
- Dubai Legislation Portal - Law No. (8) of 2007 Concerning Escrow Accounts for Real Estate Development
- Dubai Legislation Portal - Decree No. (33) of 2020 Concerning the Special Tribunal for Unfinished and Cancelled Real Property Projects
- Dubai Legislation Portal - Law No. (9) of 2009 Amending Law No. (13) of 2008 (historic version)
- Afridi & Angell - Off-Plan Construction Delays: Options for Resolution in Dubai (2019)
- Gulf News - Dubai court orders developer to refund Dh185,000 to investor over construction delays (2026)
- Khaleej Times - Dubai's off-plan property rules: can buyers get a refund if a project gets cancelled (22.1.2025)
- DIFC Courts - Hackett v Hania [2017] DIFC SCT 034
- LexisMiddleEast - Federal Decree-Law No. 25 of 2025 (Civil Transactions Law)
- HCCH - Apostille Convention status table