In brief
When RERA cancels an Off-plan project in Dubai by a final and reasoned decision, the developer must refund buyers all their payments, under Article 11(b) of Law 13 of 2008 as worded by Law 19 of 2020, and in accordance with the procedures of Escrow Law 8 of 2007. The refund is pursued mainly before a special tribunal for unfinished and cancelled projects established by Decree 33 of 2020, which can order the escrow agent to refund funds, and whose decisions are final and enforced through Dubai Courts. Money that reached the project's Escrow account is protected from the developer's creditors; money paid outside it becomes an ordinary claim against the developer, so this distinction is the first question.
Key takeaways
- 1Cancellation of a project by a final and reasoned RERA decision obliges the developer to refund all payments (Article 11(b) of Law 13/2008, as worded by Law 19/2020).
- 2The funds in the project's Escrow account cannot be attached for the developer's debts (Article 9 of Law 8/2007), and the escrow agent must act towards completion or refund (Article 15).
- 3The forum is the Special Tribunal for unfinished and cancelled projects (Decree 33/2020). The Dubai courts, including the DIFC, do not accept new claims in matters within its jurisdiction.
- 4The tribunal's decisions are final and not subject to appeal in the ordinary way, and they are enforced through the execution court of Dubai Courts. Filings with the tribunal are exempt from court fees.
- 5"Under review for cancellation" is not "cancelled". The right to a full refund arises with a final RERA decision.
A notice that the project in which you bought an Off-plan apartment has been "cancelled" is a difficult moment, but in Dubai, unlike many countries, there is a defined statutory route for it: a duty of full refund, a dedicated Escrow account, and a special tribunal that deals only with such projects. This guide explains exactly what the law guarantees, how to verify that the project has indeed been officially cancelled, what the difference is between money in the Escrow account and money that did not reach it, and the order of steps to get the money back. On the general framework of the Escrow account see the Escrow account in Off-plan: what Law 8/2007 guarantees the buyer.
The short answer
If RERA cancelled the project by a final and reasoned decision, you are entitled to a refund of all the payments you made to the developer, under Article 11(b) of Law 13 of 2008 as amended by Law 19 of 2020. The refund is claimed before the special tribunal under Decree 33 of 2020, which can order the escrow agent to pay out of the project account. To the extent your payments were deposited in the Escrow account and are well documented, the chance of getting them back is much higher.
Why are projects in Dubai cancelled?
A project is cancelled when the regulator concludes that the developer will not carry it out. According to a review by Afridi & Angell, RERA may cancel a project when the developer fails to carry it out because of gross negligence or when it has no intention of carrying it out (Article 23 of Executive Council Resolution 6 of 2010). In parallel, the escrow law sets grounds for striking a developer off the register, including bankruptcy, failure to start construction within six months of approval of the Off-plan sale without an acceptable reason, cancellation of the licence and breaches of the law (Article 17 of Law 8/2007).
According to Khaleej Times, cancellation usually results from severe delays, defaults or failure to meet regulatory requirements. Before the final decision, the project may be in an interim status of review for cancellation, in which RERA examines the progress, the developer's financial position and its compliance with the requirements, and finally cancels or allows it to continue.

What does the law say about refunds in a cancelled project?
Three pieces of legislation work together: the interim register law (13/2008) sets the duty to refund, the escrow law (8/2007) sets where the money should be and how it is refunded, and Decree 33/2020 sets who decides.
| Provision | What it provides | What it means for the buyer |
|---|---|---|
| Article 11(b) of Law 13/2008 (as worded by Law 19/2020) | When RERA cancels a project by a final and reasoned decision, or when construction has not begun for reasons beyond the developer's control and without its negligence, the developer refunds all payments, according to the procedures of Law 8/2007 | A right to a full refund, without deduction of percentages |
| Article 11(f)-(g) | The rules are part of public policy, an action contrary to them is void, and the buyer's right to apply to a court or to arbitration is preserved | A contract clause waiving the refund is not valid |
| Article 9 of Law 8/2007 | A separate Escrow account for each project, the funds are designated for its construction only and cannot be attached | The money in the account is not swallowed up by the developer's debts |
| Article 12 of Law 8/2007 | Depositors or their representatives may inspect their records and copy them | A basis for requesting a breakdown of the payments recorded in your favour |
| Article 15 of Law 8/2007 | When a project will not be completed due to emergency circumstances, the escrow agent consults the DLD and acts to complete the project or refund the depositors | A statutory mechanism that starts even without a personal claim |
| Articles 6, 7, 11 of Decree 33/2020 | The special tribunal decides on buyers' rights, may appoint auditors at the developer's expense to verify payments, order the escrow agent to refund funds, and transfer an unfinished project to another developer. Its decisions are final and enforced through Dubai Courts | A single forum, with direct authority over the Escrow account |
In earlier versions of Article 11 (Law 9/2009 and Law 19/2017) a developer could retain up to 30% of the payments when construction had not begun. Law 19/2020 abolished that option. Anyone receiving a letter citing the old wording should check it against the updated wording, which also applies to contracts signed before it came into force (Article 11(d)).
"Cancelled", "under review for cancellation" or "unfinished" - what is the difference?
The terms sound similar, but only a final cancellation triggers the duty of full refund. So the first step is to find out officially what the status is.
| Status | What it means | What happens to the money |
|---|---|---|
| Under review for cancellation | RERA is examining the project and has not yet decided | There is not yet a right to a full refund by virtue of cancellation; the contract is in force |
| Unfinished project | Construction began and stopped (Article 1 of Decree 33/2020) | The tribunal can order completion, transfer to another developer or a refund |
| Cancelled project | A final and reasoned RERA decision, or a project referred to the tribunal and not yet liquidated | A duty to refund all payments, and liquidation of the project before the tribunal |
It is important to know that even after cancellation, RERA may ask the tribunal to stay the liquidation of the project for reconsideration (Article 9 of Decree 33/2020). In other words, a project sometimes "comes back to life" with another developer, and then the question is whether completion or a refund is better for you, and what you can demand.
What to do now - step by step
This is the right way to act from the moment you learn of a cancellation or a review for cancellation:
- Find out the official status: whether there is a final and reasoned RERA decision, or the project is under review. Do not rely on a notice from a marketer or a buyers' group.
- Collect all proof of payment: SPA, Oqood confirmation, receipts, bank transfer confirmations, and the number of the Escrow account into which each payment was transferred.
- Map what was paid where: payments into the project's Escrow account; payments into another account of the developer; fees paid to the DLD; commissions to the broker. Each category has a different route.
- Request a breakdown from the escrow agent or through the lawyer: which payments were recorded in your favour in the project account. Article 12 of Law 8/2007 allows depositors to inspect their records.
- File a claim with the special tribunal: through a licensed local lawyer, with the documents in Arabic as needed. Under Article 13 of Decree 33/2020, filings are exempt from court fees.
- Follow the RERA report and the auditors' findings: the tribunal may appoint auditors at the developer's expense to verify the payments and the amounts in the account. Any discrepancy should be raised immediately.
- Consider offers of completion or transfer to another developer: if completion is offered instead of a refund, check the timetable, specification, additional payments, and what happens to the right to a refund if you agree.
- Enforce the decision: the tribunal's decision is enforced through the execution court of Dubai Courts (Article 11 of the Decree).
- Bring the money back to Israel in a documented way: with the decision, the original payment confirmations and correspondence, so that the Israeli bank can identify the source.
A payment into a general account of the developer, into a marketer's account or in cash does not enjoy the protection of Article 9 of Law 8/2007. It is still a debt of the developer to you, but in competition with other creditors, and if the developer is insolvent, in the insolvency proceedings. At the same time, Law 8/2007 provides for penalties, including imprisonment and a fine of at least AED 100,000, for misuse of project funds (Article 16). See the developer is in difficulty or insolvent: what protects the buyer.
What is included in "all payments"?
The law refers to all the payments the buyers made to the developer. Fees paid to the DLD for Oqood registration and commissions paid to the broker are not payments to the developer, and it is not certain that they form part of the refund from the Escrow account. As for brokerage commission, according to Afridi & Angell a broker is usually entitled to a commission only when the deal has been completed, unless otherwise agreed (Articles 30 to 32 of By-Law 85 of 2006), so it is worth checking the brokerage agreement and claiming the commission separately. Interest and compensation beyond the refund are an open question that depends on the circumstances and the forum.
How long does it take to get the money?
We did not find a fixed statutory deadline for a refund in a cancelled project. Article 11(a) sets a deadline of one year from termination, or 60 days from resale of the unit, whichever is earlier, but it applies to termination because of the buyer's default. In a project cancelled by RERA, Article 11(b) refers to the procedures of Law 8/2007, and the actual refund depends on the proceedings before the tribunal, the verification of payments and the state of the Escrow account. It is advisable to prepare for a process of months, not days.
How to prevent this in advance
- Check that the developer is registered with the DLD and that the project is approved and registered before the first payment. A contract for a project that has not been approved is void (Article 10 of Law 13/2008).
- Pay only into the project's Escrow account, and verify the account number against the project documents and not only against a marketer's email.
- Make sure of Oqood registration in your name. A sale not registered in the interim register is void (Article 3 of Law 13/2008). See Oqood registration: the Off-plan buyer's protection until handover.
- Check that the advertising through which you learned of the project was approved. Advertising and exhibitions of Off-plan sales, including abroad, require the DLD's written approval (Article 5 of Law 8/2007).
- Check the developer's history and rate of progress in previous projects. See how to check a developer in Dubai before paying.
- Keep an organised file of every payment from day one.
Common mistakes
- Stopping payment when the project is only "under review": as long as there is no final decision, the contract is in force, and the developer can open a default procedure under Article 11(a).
- Filing a claim in an ordinary court or in the DIFC: in matters within the special tribunal's jurisdiction, the courts do not accept new claims, and pending cases are transferred to it (Article 10 of Decree 33/2020).
- Signing a waiver in return for a quick partial refund: the rules of Article 11 are public policy, but a settlement agreement signed voluntarily can complicate a later claim.
- Not documenting payments: the tribunal verifies amounts against the account records; a payment without a supporting document is hard to prove.
- Relying on a notice citing "retention of 30%": that is the old wording.
What about the Israeli side?
A refund of an amount you paid is not income in the ordinary sense, but compensation, interest or exchange-rate differences may have tax significance, and anyone who reported the property should update. When transferring the money back, the Israeli bank will ask for documents: the decision, the original payment confirmations and the correspondence. See the Israeli side of activity abroad and delayed transfers abroad and source of funds.
Before you sign / how we assist
We assist Israeli buyers in coordination with licensed local lawyers in Dubai: before the deal, in checking the developer's registration, the project approval and the Escrow account; and after cancellation, in mapping the payments, clarifying the official status, preparing the claim to the special tribunal and coordinating the return of the funds to Israel. A related situation, in which the project is still being built but is delayed, is described in the developer is late with handover: what are your rights.
This guide is general information current as of November 2026 and does not constitute legal advice. The legislative texts were quoted from the official English translation on the Dubai Legislation Portal, and the Arabic text prevails. Each case is examined on its own merits with a licensed local lawyer.
Frequently asked questions
The Dubai project was cancelled - am I entitled to a full refund?
If RERA cancelled the project by a final and reasoned decision, yes. Article 11(b) of Law 13/2008, as worded by Law 19/2020, obliges the developer to refund all the payments the buyers made, according to the procedures of Escrow Law 8/2007.
Who refunds the money - the developer or the Escrow account?
The obligation is the developer's, but in practice the refund is made mainly from the project's Escrow account. The special tribunal under Decree 33/2020 may order the escrow agent or the developer to take actions, including refunding funds.
Where do you file a refund request in a cancelled project?
With the Special Tribunal for unfinished and cancelled projects, whose main office is at the DLD. The Dubai courts, including the DIFC, do not accept new claims in matters within its jurisdiction. Filings are exempt from court fees.
Can the special tribunal's decision be appealed?
Under Article 11 of Decree 33/2020, the decisions are final and not subject to appeal in the ordinary way. They are enforced through the execution court of Dubai Courts.
How long does it take to get the money from a cancelled project?
The law does not set a uniform deadline for a refund in a project cancelled by RERA. The deadline of one year or 60 days from resale applies to termination because of buyer default. In practice the refund depends on the proceedings before the tribunal and the verification of payments, and it is advisable to prepare for months.
What happens if I paid directly to the developer and not into the Escrow account?
The payment still creates a debt of the developer to you, but it is not protected from creditors like escrow funds. You need to claim it from the developer, and if the developer is insolvent, file a proof of debt in the proceedings. Misuse of project funds is also an offence under Article 16 of Law 8/2007.
Are the 4% I paid to the DLD and the broker's commission also refunded?
Not certain. The law refers to payments to the developer. The Oqood fee was paid to the authority and the brokerage commission to the broker, so each must be checked separately, including the brokerage agreement.
The project was cancelled and now another developer wants to complete it. Do I have to agree?
The tribunal may transfer an unfinished project to another developer, and RERA may ask to stay liquidation for reconsideration. Before agreeing, it is advisable to check the terms: timetable, specification, additional payments, and what happens to the right to a refund.
Do I need to come to Dubai to get a refund?
Usually not. The proceedings can be conducted through a licensed local lawyer with an appropriate power of attorney. A power of attorney from Israel requires the full authentication chain and translation into Arabic, because the UAE is not a party to the Apostille Convention.
Read next · 12 min readYour Partner or Client in Dubai Has Stopped Paying - How Do You Sue? Debt Collection Routes, Arbitration and LitigationPartner or client in Dubai not paying? What to do: check the contract, demand letter, payment order, bounced cheque, DIAC arbitration, DIFC, attachment, Israel.Read the guideSources
- Dubai Legislation Portal - Law No. (19) of 2020 amending Law No. (13) of 2008 (Article 11)
- Dubai Legislation Portal - Law No. (8) of 2007 Concerning Escrow Accounts for Real Estate Development
- Dubai Legislation Portal - Decree No. (33) of 2020 Concerning the Special Tribunal for Unfinished and Cancelled Real Property Projects
- Dubai Legislation Portal - Law No. (13) of 2008 Regulating the Interim Real Property Register
- Dubai Legislation Portal - Law No. (9) of 2009 Amending Law No. (13) of 2008 (historic version)
- Khaleej Times - Dubai's off-plan property rules: can buyers get a refund if a project gets cancelled (22.1.2025)
- Afridi & Angell - Off-Plan Construction Delays: Options for Resolution in Dubai (2019)
- Afridi & Angell - Purchasing and Selling Commercial Real Estate, Emirate of Dubai (April 2026)
- BSA - Navigating Dubai's off-plan real estate laws: compliance essentials for developers (2025)
- HCCH - Apostille Convention status table