Handover of an Apartment in Dubai: Snagging Inspection, Defects and the Developer's Liability

Apartment handover in Dubai for an Israeli buyer: what Snagging checks, recording defects, developer liability under Law 6/2019 and the Civil Code, remotely.

By Adv. Ilan LeibovitchUpdated: 11 min read
Purchase processPl. IX·377

In brief

Handover of an apartment in Dubai usually includes a completion notice, payment of the balance and the fees, a defects inspection (Snagging) and signing a handover protocol. Dubai has no dedicated statutory provision for an inspection before handover, so the right to an inspection and to repairs is set mainly in the contract. After handover statutory protections apply: under Law 6/2019 the developer is liable for defects in the structure of the common property for 10 years from the completion certificate and for defective installations for one year, and under the new federal Civil Code the main contractor and the engineer are liable for 10 years for defects that endanger the building's stability. Orderly documentation on the day of handover is the buyer's most important tool.

Key takeaways

  1. 1After the completion certificate, the developer may not refuse to hand over a unit to a buyer who has met his obligations, and must also register an allocated parking space in his name (article 7 of Resolution 6/2010).
  2. 2Snagging is a contractual practice, not a statutory obligation. What was not documented on the day of handover is harder to claim later.
  3. 3Law 6/2019 (article 40): the developer's liability for defects in the structure of the common property for 10 years from the completion certificate, and for defective installations for one year.
  4. 4Federal Civil Code 25/2025, in force from 1.6.2026: strict 10-year liability of the main contractor and the engineer for defects that endanger stability or safety, and a limitation period of 3 years from discovery of the defect.
  5. 55% of the escrow account remains with the trustee for one year after the units are registered in the buyers' names, and according to the DLD it serves as a guarantee for repairing defects.

Most Israeli buyers in Dubai are not there on the day of handover. The notice arrives by email, with a demand to pay a balance and fees and to set a date for receiving the key, sometimes with a short deadline. This is the stage at which it is decided whether defects will be repaired at the developer's expense or at yours. This guide explains what happens at handover in Dubai, what is worth checking, how to document, what the developer's liability under the law is after handover, and how to manage all of this from Israel.

What happens at the handover of an apartment in Dubai, step by step?

Handover begins when the project receives a Completion Certificate from the authorities. From that moment several rules apply: the developer must register the project in the DLD permanent register, the units of buyers who have met their obligations are registered in their names (article 8 of Law 13/2008), and the developer may not refuse to hand over the unit to them, even if they have other debts to the developer unrelated to the unit (article 7 of Resolution 6/2010).

  1. Completion notice: the developer announces that the project has been completed and specifies the balance payable, the fees and the documents required.
  2. Payment of the balance: according to the payment schedule in the contract. In a Post Handover plan part of the balance is deferred.
  3. Defects inspection (Snagging): a walk-through of the unit before receiving the key, usually with a written list of defects.
  4. Repair and re-inspection: the developer repairs the defects recorded, and the unit is inspected again.
  5. Handover protocol and receipt of the key: signing a handover document, preferably with the list of reservations attached.
  6. Registration and certificate of ownership: transfer from the interim register (Oqood) to the permanent register and issue of a Title Deed for units paid in full, according to the DLD.

Is there a statutory obligation to carry out a Snagging inspection before handover in Dubai?

We did not find in Dubai law a dedicated provision requiring a defects inspection before handover. Snagging is an accepted, contractual practice. So the important questions are what your contract says: whether you have a right to an inspection before receiving the key, within how long the developer repairs, whether signing the handover protocol is considered a waiver of claims, and whether there is a defects period after handover. If the contract is silent, your rights rest on the general law and on your documentation.

Do not sign a clean acceptance

If there are defects, write them on the handover protocol or attach a signed list, and state that acceptance is subject to their repair. Signing a document stating that the apartment was received in proper condition without reservation may make a later claim more difficult.

Dubai

What is checked on the day of handover?

A good inspection compares the apartment with three documents: the contract and the specification appendix, the unit plan, and the marketing materials that formed part of the agreement. The following list suits a professional inspector or an attorney-in-fact:

AreaWhat is checkedWhy it matters
Area and layoutRoom dimensions against the plan, number of rooms, balconyAn area smaller by more than 5% of the net area entitles to compensation under the regulations
Specification and finishesFlooring, kitchen, cupboards, appliances, cladding against the specification appendixA material deviation from the specification is a legal cause of action
SystemsAir conditioning, electricity, plumbing, drainage, hot waterDefective installations are covered by a one-year warranty under Law 6/2019
Damp and cracksStains, cracks in walls and ceiling, sealing of windows and balconiesA structural defect may fall within a longer liability
Parking and storageThat the location and number match what was allocatedThe developer must also register an allocated parking space in your name
Common propertyLobby, lifts, pool, facilities that were promisedThe developer's structural liability applies to the common property

Document every defect with a dated photograph, at a clear location, and obtain the developer's written confirmation of the list. If there is a gap in area or in a material component, see the guide to an apartment that differs from the specification.

What is the developer's liability for defects after handover in Dubai?

There are two main layers of statutory liability, and alongside them the contract:

  • Dubai Law 6/2019, article 40: the developer is liable for repairing defects in the structure of the common property for 10 years from the date of the completion certificate, and for repairing or replacing defective installations (mechanical, electrical, plumbing, sewage) for one year. The sources disagree as to whether the one year for installations runs from handover to the owner or from the completion certificate, so it is worth reporting defects as early as possible.
  • The new federal Civil Code: Federal Decree-Law 25/2025, which came into force on 1.6.2026 and replaced the 1985 Civil Transactions Law, provides in articles 821-824 for a 10-year liability from handover, jointly and severally, of the main contractor and the engineer for total or partial collapse and for defects that endanger the building's stability or safety. This is strict liability, a condition exempting from it or limiting it is void, and the limitation period is 3 years from discovery of the defect. Contracts signed before 1.6.2026 remain mainly under the previous law, and the interpretation of the transitional rules is not uniform.
  • The contract: most contracts set their own warranty or defects period. It can add to the law, but cannot detract from provisions that the law has made mandatory.

The regulations under Law 13/2008 add a strong tool: a buyer may ask the court to rescind the contract if it is proved that the unit is unfit for use because of material construction defects after handover (article 20(4) of Resolution 6/2010). This is a route for serious cases, not for finishing defects.

What is the role of the 5% that remains in the escrow account?

Law 8/2007 provides that after the completion certificate the trustee holds 5% of the account and releases it to the developer one year after the units have been registered in the buyers' names (article 14). The DLD describes this amount as a guarantee for repairing defects. It is not money paid directly to the buyer, but it is one of the reasons it is worth reporting defects in the first year, while the developer still has money waiting to be released. More on the mechanism in the guide to the escrow account.

From when are service charges paid, and what else begins at handover?

The Dubai Rental Disputes Center held in 2025 that a buyer registered in the interim register is liable for service charges from the date the project is completed, or from the date he defaulted on payment, even before ownership was transferred to him. Service charges require RERA approval of the budget under Law 6/2019, and the approved amounts per project can be checked in the DLD service charge index. In addition, electricity and water bills begin, and if you let, registration of the tenancy contract in Ejari.

How do you take delivery of an apartment in Dubai from Israel?

You can use a local professional inspector for the defects inspection, and appoint an attorney-in-fact to sign the handover protocol and receive the key. A power of attorney signed in Israel must pass through an authentication chain, because the United Arab Emirates is not a party to the Apostille Convention: authentication at the Israeli Ministry of Foreign Affairs, at the UAE embassy in Tel Aviv, and as necessary at the UAE Ministry of Foreign Affairs, with a legal translation into Arabic. It is worth drafting the power of attorney so that it expressly includes taking possession, signing handover documents with reservations and acts before the DLD, and preparing it in advance, before the completion notice arrives. On the documents worth receiving and keeping at handover see also the guide to the handover file for a property abroad.

What do you do when the developer does not repair defects?

  1. Send the developer a written demand with the list of defects, the photographs and a reference to the warranty clause in the contract and to Law 6/2019.
  2. Set a reasonable deadline for the repair and document every response.
  3. For a defect in the common property, also contact the management company and the owners' committee.
  4. Consider an engineer's opinion, which will also serve in proceedings.
  5. Check the dispute resolution clause in the contract: arbitration or the Dubai courts. Under the regulations, the DLD may also mediate between a developer and a buyer, and a settlement approved by it is binding (article 14 of Resolution 6/2010).

On choosing the route in a dispute with a developer abroad see the guide to arbitration or court against a developer.

Before you sign: how we assist

We prepare the handover even before the completion notice: we check what the contract says about inspection and liability, prepare an authenticated power of attorney for taking delivery of the apartment remotely, and draft the reservations for the protocol. The engineering inspection on site and the acts before the authorities in Dubai are carried out in coordination with locally licensed professionals and lawyers. If defects are discovered, we accompany the demand to the developer and the decision on proceedings.

General information, not legal advice

The information in this article is general and correct as of November 2026, and is not legal or engineering advice for a particular transaction. The new Civil Code came into force on 1.6.2026 and its transitional rules are still being interpreted, so the law applying to the specific contract should be checked.

Frequently asked questions

Is Snagging mandatory in Dubai?

There is no dedicated statutory provision requiring it; it is an accepted contractual practice. Nevertheless, inspecting and documenting before receiving the key is the best way to preserve the right to repairs at the developer's expense.

How long is the developer liable for defects in Dubai?

Under Law 6/2019, 10 years for defects in the structure of the common property from the completion certificate, and one year for defective installations. Under the new federal Civil Code, the main contractor and the engineer are liable for 10 years from handover for defects that endanger stability or safety. The contract can add warranty periods.

The developer is not handing over my apartment even though the project has been completed. What do I do?

Under article 7 of Resolution 6/2010, after the completion certificate the developer may not refuse to hand over a unit to a buyer who has met his obligations, and if it refuses, the DLD may register the unit in the buyer's name at his request. It is worth seeking advice and checking what else the contract requires.

Can you take delivery of an apartment in Dubai without flying?

Yes, through a professional inspector and an attorney-in-fact. A power of attorney from Israel needs an authentication chain and a translation into Arabic, because the United Arab Emirates is not a party to the Apostille Convention. It is worth preparing it in advance.

I signed a handover protocol without reservations. Have I lost my rights?

Not necessarily. Liability under Law 6/2019 and under the Civil Code does not depend on the protocol, and a condition exempting from the 10-year liability is void. But visible finishing defects that were not recorded are harder to claim, so it is worth acting quickly and documenting.

From when do I pay service charges on a new apartment in Dubai?

According to a 2025 decision of the Rental Disputes Center, from the date the project is completed, even before the transfer of ownership. The amounts require RERA approval and can be checked in the DLD service charge index.

What is the 5% that remains in the escrow account?

Under Law 8/2007, after the completion certificate the trustee holds 5% of the escrow account and releases it to the developer one year after the units are registered in the buyers' names. The DLD describes this as a guarantee for repairing defects.

Read next · 8 min readA Business Bank Account in Dubai for an Israeli-Owned Company: What the Bank Checks and How to PrepareOpening a business bank account in Dubai for an Israeli-owned company: KYC, beneficial owners, source of funds, authenticating Israeli documents, mistakes.Read the guide

Sources

  1. Afridi & Angell - Law No. 6 of 2019 on the Ownership of Jointly Owned Real Property in Dubai
  2. LexisMiddleEast - Federal Decree-Law No. 25 of 2025 (Civil Transactions Law)
  3. Charles Russell Speechlys - Decennial liability under the new UAE Civil Code, Articles 821 to 824
  4. Dubai Legislation Portal - Executive Council Resolution No. (6) of 2010
  5. Dubai Legislation Portal - Law No. (8) of 2007 Concerning Escrow Accounts
  6. Dubai Land Department - Frequently Asked Questions
  7. Dubai Rental Disputes Center - new legal principle on real estate service fees

Let’s start with a conversation.

A sound international transaction begins long before signing. A short introductory call will clarify whether, and how, we are the right firm to support you.

Not ready for a call yet? Deal readiness check · Get the monthly newsletter

Office
7 Hanafat HaDegel St., Ness Ziona, Israel
Romania
Meetings in Bucharest by prior arrangement
  • Hebrew · Romanian · English
  • Ness Ziona · Bucharest meetings by appointment
  • Online meetings