A dispute with a developer abroad is conducted in the place and in the manner set by the contract, within the limits allowed by the law of the country where the property is located: claims over ownership of the property itself usually belong to the courts of the country where it is situated, while a monetary claim under the contract leaves more room for choice. The important question is not only where you file, but where you can enforce: an Israeli judgment requires recognition proceedings in the other country, and an arbitral award is enforced under the New York Convention. That is why the jurisdiction, governing law and arbitration clauses are settled before signing, according to where the developer's assets are located.
Key takeaways
- 1Three separate questions: where the case is heard (jurisdiction), under which law (governing law), and where you collect (enforcement).
- 2In the European Union, a claim concerning a right in rem in a property belongs exclusively to the courts of the country where the property is located, and a clause in the contract does not change that.
- 3An Israeli judgment is not enforced automatically abroad, and in Romania its recognition is subject, among other things, to reciprocity and to the exclusive jurisdiction of the courts there.
- 4A foreign arbitral award is enforced under the New York Convention, to which Israel and Romania are parties, but some countries apply it only to commercial relationships.
- 5In Romania, an arbitration, governing law or jurisdiction clause in a standard-form contract is valid only if the buyer accepted it expressly and in writing.
Most buyers read the price, the payment schedule and the delivery date in a contract with a developer. The clause at the end, the one that determines where a dispute will be heard, looks technical. It becomes important on the day something goes wrong: a long delay, a demand for a refund, a disagreement over the specification. On that day it determines in which country you will have to act, in which language, under which law, and whether the judgment you obtain will be worth anything.
This guide explains the difference between a jurisdiction clause, a governing law clause and an arbitration clause, what the law allows you to set in the contract and what it does not, how a judgment or an arbitral award is enforced across borders, and what to do in the first weeks of a dispute.
What determines where a dispute with a developer abroad will be heard?
The short answer: the contract, within the limits set by the law of the country where the property is located. It is worth separating three questions, because each of them is determined differently:
| The question | What determines it | What you should know |
|---|---|---|
| Where the case is heard (jurisdiction) | The jurisdiction or arbitration clause in the contract, and the jurisdiction rules of the relevant countries | Claims concerning a right in rem in the property usually belong to the country where the property is located, regardless of the contract |
| Under which law (governing law) | The governing law clause, and in its absence the conflict-of-laws rules | In the European Union, absent a choice, a contract concerning a right in rem in a property is governed by the law of the country where the property is located |
| Where you collect (enforcement) | The place where the other party's assets or funds are located | A judgment that cannot be enforced where there are assets is mainly a declaration |
What is the difference between a jurisdiction clause, a governing law clause and an arbitration clause?
- A jurisdiction clause determines which courts a dispute will be brought before. It can be exclusive, meaning only those courts, or non-exclusive, meaning they have jurisdiction without excluding others. Israeli case law has held that the wording alone does not always decide this question, and that a party claiming the clause is exclusive has to show it. It is therefore better to write “exclusively” in so many words.
- A governing law clause determines under which law the contract will be interpreted. Under the European Union's Rome I Regulation, the rule is that the contract is governed by the law chosen by the parties. This clause is separate from the question of venue: a court in one country can apply the law of another country, but the foreign law must then be proven to it.
- An arbitration clause takes the dispute out of the courts to an arbitrator or an arbitral tribunal. Arbitration exists only if the parties agreed to it, and the agreement must be in writing.
The common problem is a mismatch between the clauses: jurisdiction in Israel, Romanian law and a property in Romania, or two conflicting clauses, one in the contract and one in an annex. Every such combination adds a preliminary proceeding over where the case should be heard at all, before you reach the question of who is right.

Can the contract provide that the dispute will be heard in Israel?
It can be written, but it will not always hold, and even when it holds, it will not necessarily help. In the European Union, under Article 24(1) of Regulation 1215/2012 (Brussels I Recast), in proceedings which have as their object rights in rem in immovable property or tenancies of immovable property, exclusive jurisdiction lies with the courts of the country where the property is situated, regardless of the domicile of the parties. Under Article 25(4) of the Regulation, a jurisdiction agreement that attempts to circumvent such exclusive jurisdiction has no legal force.
In Romania, the Code of Civil Procedure grants exclusive jurisdiction to the Romanian courts in international disputes concerning immovable property in Romania (Article 1079), and lists such exclusive jurisdiction among the grounds for refusing to recognise a foreign judgment (Article 1096). The practical meaning: a claim in Israel concerning ownership of an apartment in Romania may end in a judgment that will not be recognised there.
In a monetary claim under the contract, for example the return of advance payments or agreed compensation for delay, there is more room for choice. But even then, if the developer's assets are abroad, an Israeli judgment will have to go through recognition proceedings in that country. In Romania, recognition of a judgment from a country that is not a member of the European Union is subject to cumulative conditions: the judgment is final under the law of the country that gave it, the court that gave it had jurisdiction under that country's law, and there is reciprocity between Romania and that country in the recognition of judgments (Article 1095). On what happens in practice when Israeli jurisdiction is chosen for a partnership in a property in Romania, you can read the story from the weekly column about an Israeli jurisdiction clause.
The right question is not “where is it convenient for me to sue”, but “where will I be able to collect”. If the developer's property, account and company are in one country, a judgment from that same country saves an entire stage of recognition.
Arbitration or court: which suits a dispute with a developer?
There is no single answer. Arbitration is suitable mainly when the amounts are large, when the parties are from different countries and when it is important that the award be enforced in several countries. A local court is more suitable when the dispute concerns the registration of the property itself, or when the amount does not justify the costs of arbitration, which the parties bear themselves.
| Court in the country of the property | International arbitration | |
|---|---|---|
| When it applies | Always, unless otherwise agreed | Only if the parties agreed in writing |
| Language | The language of the country | As agreed by the parties |
| Who decides | A local judge | An arbitrator or panel that the parties choose or appoint under the institution's rules |
| Appeal | Under local civil procedure | Very limited; setting aside an arbitral award is possible only on narrow grounds |
| Costs | Court fees and legal fees | Also the arbitrators' fees and the institution's fees, at the parties' expense |
| Enforcement in another country | Under the recognition rules of the enforcing country | Under the New York Convention, in the countries that are party to it |
| Orders concerning registration of the property | Directly, in the country of the property | Usually require an additional proceeding in a local court |
Two things are particularly important for a private buyer. First, in Romania, an arbitration clause, a governing law clause or a clause that departs from the rules of jurisdiction, when included in a standard-form contract drafted in advance by the developer, is valid only if the buyer accepted it expressly and in writing (Article 1203 of the Romanian Civil Code). See also the guide on unfair clauses in a developer contract in Romania. Second, some countries, including Romania, Cyprus and the USA, declared that they will apply the New York Convention only to relationships that their law considers commercial. Whether buying an apartment for private use meets that definition is a question to check locally before choosing arbitration.
How is a judgment or an arbitral award enforced across borders?
A judgment is paper until it is enforced where the other party has money or assets. Each direction of enforcement follows a different route:
| What you hold | Where it is enforced | The framework |
|---|---|---|
| A foreign judgment against someone with assets in Israel | A court in Israel | Foreign Judgments Enforcement Law, 5718-1958: the judgment was given by a competent court, is no longer appealable, is enforceable in the country that gave it and does not contradict public policy; reciprocity is required; the application is filed within five years of the date of the judgment, unless otherwise provided |
| An Israeli judgment against a developer with assets in Romania | A court in Romania | Romanian Code of Civil Procedure, Articles 1095-1096: finality, jurisdiction, reciprocity, and grounds for refusal such as public policy and the exclusive jurisdiction of the Romanian courts |
| An arbitral award given abroad | Any country that is party to the New York Convention | The New York Convention (1958); in Israel, section 29A of the Arbitration Law, 5728-1968, refers to the provisions of the Convention |
| A judgment of one European Union country, for enforcement in another European Union country | The enforcing country | Regulation 1215/2012, which is based on recognition between European Union member states |
The New York Convention lists a closed set of grounds for refusing to enforce a foreign arbitral award, including an invalid arbitration agreement, a party that was not given proper notice or was unable to present its case, an award that goes beyond the scope of the arbitration, an award that was set aside in the country where it was made, a subject matter that cannot be settled by arbitration under the local law, and a conflict with public policy. The Convention also requires a court seized of a claim on a matter covered by an arbitration agreement to refer the parties to arbitration if one of them so requests. In Israel, section 5 of the Arbitration Law allows a party to apply for a stay of proceedings in such a situation.
What is worth negotiating before signing?
Many developers use a standard-form contract, but dispute clauses are usually among the clauses that can be discussed. These are the points worth checking in the draft:
- Who the party to the contract is. The full name of the company, its registration number and the country where it is registered. The claim will be filed against the company that signed, not against its shareholders. If there is a guarantee from a parent company or from the shareholders, it must be in writing.
- A precise jurisdiction clause. City and court, “exclusively” or not, and consistency with the law of the country where the property is located.
- A governing law that matches the place of the hearing. Foreign law in a local court means expert opinions and translations.
- If there is arbitration: the institution, the seat of arbitration, the rules, the language and the number of arbitrators. An arbitration clause without an institution and without an appointment mechanism invites a further dispute.
- The language of the contract. If there is a version in two languages, which version prevails.
- Addresses for notices. A postal and email address for each party, so that a notice is sent to an agreed place.
- A negotiation or mediation stage before a claim, limited to a set number of days, so that it does not turn into an endless delay.
- Signing the clauses. In Romania, express written acceptance of arbitration, governing law and jurisdiction clauses in a standard-form contract.
The dispute has already started: what do you do in the first weeks?
- Gather the documents: the contract and all annexes, the transfer confirmations, the correspondence with the developer and an up-to-date extract from the land registry.
- Read the dispute clauses: jurisdiction, governing law, arbitration, notices, and a negotiation stage if one was set.
- Check deadlines: in some countries there are short deadlines for certain actions. In Romania, for example, an application for a judgment to take the place of a final contract is filed within 6 months, as explained in the guide on a developer's delay in delivery in Romania.
- Send a written notice in accordance with local law: the breach is usually counted from it.
- Map the developer's assets: where the company is registered, where the project is, and which units are still registered in its name.
- Consider steps to preserve the position: interim relief or registering a caveat, as local law allows, through a lawyer licensed in the country where the property is located.
- Only then decide where to sue: a claim in Israel, when the contract provides for jurisdiction or arbitration elsewhere, may be stopped at the preliminary stage and cost time and money.
For the broader picture of what to do when a deal abroad goes wrong, from a developer who is late to an ownership problem, see the guide when a real estate deal abroad goes wrong.
What should you do before signing, and how do we assist?
Before signing, it is worth asking three questions about any contract with a developer: where will a dispute be heard, under which law, and where will I be able to collect if I win. We assist Israeli buyers and developers in reading the dispute clauses in the draft, adapting them to where the property and the developer are located, and drafting the requests for amendment before signing. When a dispute arises, representation in the courts of the country where the property is located is provided by a lawyer licensed in that country.
The above is general information, correct as of November 2026, and is not legal advice. The rules of jurisdiction, recognition and enforcement differ from country to country and depend on the wording of the contract, so every case is examined on its own merits with a lawyer in the relevant country.
Frequently asked questions
Can I sue in Israel a foreign developer who sold me an apartment?
Sometimes a claim can be filed, but it is not always effective. If the contract provides for exclusive jurisdiction or arbitration elsewhere, the claim may be stopped at the preliminary stage. And if the developer's assets are abroad, the Israeli judgment will need recognition proceedings in that country, and in Romania recognition is subject, among other things, to reciprocity and to the exclusive jurisdiction of the courts there in immovable property matters.
Can a contract provide that a dispute over an apartment abroad will be heard in Israel?
In a dispute over ownership or rights in rem in the property - usually not. In the EU, under Regulation 1215/2012 (Brussels I recast), exclusive jurisdiction in such matters lies with the courts of the state where the property is located, and a jurisdiction agreement that tries to circumvent it has no effect. In a money claim under the contract there is more room for choice, but an Israeli judgment will need a recognition procedure in the state where the developer's assets are located.
What is the difference between an exclusive jurisdiction clause and a non-exclusive one?
An exclusive clause provides that only the chosen courts have jurisdiction. A non-exclusive clause gives them jurisdiction without excluding others. Since the wording is not always decisive, it is worth writing “exclusively” in so many words if that is the intention.
Arbitration or court - which is better in a dispute with a developer abroad?
There is no single answer. Arbitration suits mainly large amounts, parties from different countries and cases where the award must be enforced in several countries under the New York Convention. A local court is more suitable when the dispute concerns the registration of the property itself, or when the amount does not justify the costs of arbitration, which the parties bear themselves.
Is an arbitral award enforced in every country?
A foreign arbitral award is enforced under the New York Convention in the countries that are party to it, including Israel and Romania. However, some countries limited the Convention to commercial relationships, and the Convention lists defined grounds for refusal, such as an invalid arbitration agreement or a conflict with public policy.
Does the arbitration clause in the developer's contract in Romania bind me?
In a standard-form contract drafted in advance by the developer, an arbitration clause is valid under Article 1203 of the Romanian Civil Code only if you accepted it expressly and in writing. If you did not sign it separately, it is worth checking the question with a Romanian lawyer.
How long do you have to enforce a foreign judgment in Israel?
Under the Foreign Judgments Enforcement Law, the court will not consider an application filed more than five years after the date of the judgment, unless otherwise agreed between Israel and the other country or the court found special reasons for the delay.
Read next · 10 min readPermanent Establishment and a Remote Employee Abroad: When an Israeli Company Is Taxable in the Employee's Country, and What About Payroll and Social SecurityAn employee working from home abroad may create a permanent establishment for an Israeli company. Fixed place, dependent agent, building site, OECD 2025 home office update, payroll.Read the guideSources
- Foreign Judgments Enforcement Law, 5718-1958 - Wikisource (Hebrew)
- Arbitration Law, 5728-1968 - Wikisource (Hebrew)
- New York Convention - Contracting States
- New York Convention (1958) - text
- Regulation (EU) No 1215/2012, Article 24 (legislation.gov.uk, version of 31.1.2020)
- Regulation (EU) No 1215/2012, Article 25 (legislation.gov.uk, version of 31.1.2020)
- Regulation (EC) No 593/2008 (Rome I), Articles 3 and 4 (legislation.gov.uk)
- Codul de procedură civilă, art. 1079, 1095, 1096 (legeaz.net)
- Codul civil, art. 1203 - Clauze neuzuale (codulcivil.ro)