RERA Developer Registration in Dubai: Development Licence, Project Registration, Escrow Account and Marketing Permit for an Israeli Developer

RERA developer registration in Dubai: the DLD developer register, development licence, 8 Escrow documents, project registration, marketing permit, penalties.

By Adv. Ilan LeibovitchUpdated: 10 min read
RegulationPl. IX·336

In brief

A developer selling Off-plan units in Dubai must be registered in the developer register of the Dubai Land Department (DLD) and hold a licence from the competent authorities, under Article 4 of Law 8 of 2007. Before collecting a single dirham from buyers, it must also register the project, hold the land and obtain the planning approvals, open a dedicated Escrow account for the project, and obtain written approval to advertise. A sale made before the project was approved and registered is void, under Article 11 of Executive Council Resolution 6 of 2010.

Key takeaways

  1. 1Two separate layers: registering the company as a developer in the DLD register and a development licence, and then registering each project separately before sale.
  2. 2To open an Escrow account, 8 documents are submitted (Article 6 of Law 8/2007), including the Title Deed of the land, approved plans and a costs and revenues report certified by an accountant.
  3. 3An Off-plan sale before the project has been approved and registered with the DLD is void (Article 11 of Resolution 6/2010), and any advertising, including in Israel, requires written DLD approval (Article 5 of Law 8/2007).
  4. 4A developer that has not started construction within 6 months of approval of the Off-plan sale, without a justified reason, may be struck off the register (Article 17).
  5. 5Offences such as operating without a licence or misusing project funds: imprisonment and/or a fine of at least AED 100,000 (Article 16).

An Israeli developer arriving in Dubai is well familiar with the world of permits, bank project financing and the Sale (Apartments) Law. In Dubai the logic is similar, but the structure is different: the regulator is the Dubai Land Department (DLD) and its regulatory arm, RERA, and the legislation is based mainly on the escrow law (Law No. 8 of 2007), the interim register law (Law No. 13 of 2008) and its regulations (Executive Council Resolution No. 6 of 2010). This guide explains what is required of the company, what is required of each project, and in what order things are done so as not to get stuck halfway.

Who must register as a developer in Dubai?

Every developer that sells Off-plan units in Dubai and receives payments for them. Law 8/2007 applies to such a developer (Article 3), and the definition includes both a master developer and a sub-developer. Under Article 4, the DLD maintains a register of real estate developers, and a developer may not operate unless it is registered in it and has also obtained a licence from the competent authorities.

The practical meaning for an Israeli developer: setting up a company is not enough. You need a company with an appropriate business licence, and then its registration as a developer. According to reviews by local law firms, RERA registers as a developer a company registered with Dubai's economic licensing authority with a real estate development activity. The exact wording of the eligibility conditions and the current fees should be checked with the DLD before starting, because they are not published on a single official page.

Can a foreigner hold 100% of the development company?

Yes, in most activities. Since 2021 the federal companies law (Federal Decree-Law 32/2021) has allowed full foreign ownership of Mainland companies, with no requirement for a local partner, except for activities of strategic impact determined by the Cabinet (according to the u.ae portal, as of November 2026). However, for the purposes of land ownership, a company with any foreign shareholder is considered foreign and is restricted to areas designated for foreign ownership. On the differences between the forms of incorporation see Free Zone or Mainland.

Dubai

What is the difference between developer registration and project registration?

Developer registration is a registration of the company, made once. Project registration is made for each project separately, and only it opens the possibility of selling. Resolution 6/2010 provides in Article 4 that a developer may not start a project or sell Off-plan before it has obtained possession of the land and a demarcation certificate, before it has actual control of the land and before it has obtained the approvals of the competent authorities.

StageWhat is requiredBasis
Registering the company as a developerRegistration in the DLD developer register and a licence from the competent authoritiesArticle 4, Law 8/2007
Control of the landPossession of the land, a demarcation certificate and actual controlArticle 4, Resolution 6/2010
ApprovalsApprovals of the competent authorities for the project, and for a sub-developer also the master developer's written approval of the plans and the saleArticles 4 and 22, Resolution 6/2010
Escrow accountA separate account for the project with an approved escrow agentArticles 6-9, Law 8/2007
Advertising permitWritten DLD approval for each advertisement or exhibition, in the UAE and abroadArticle 5, Law 8/2007
Registering each saleRegistration in the interim register (Oqood) within the time set by lawLaw 13/2008 and Resolution 6/2010

Which documents are submitted to open an Escrow account and sell Off-plan?

Article 6 of Law 8/2007 lists eight documents that a developer attaches to an application to open an Escrow account and sell Off-plan. This is essentially the regulator's checklist for the project:

  1. A certificate of membership of the Dubai Chamber of Commerce.
  2. The company's commercial licence.
  3. The Title Deed (land registry extract) of the land.
  4. The contract between the master developer and the sub-developer, if any.
  5. Approved preliminary designs and engineering plans.
  6. A costs and revenues report for the project, certified by a licensed accountant.
  7. An undertaking to commence construction.
  8. The standard sale contract that will be used by buyers.
The equity required before marketing

Secondary sources attribute to Dubai legislation a requirement to deposit part of the construction cost (in cash or by guarantee) before marketing begins. We did not find the requirement in the official text of the law, so its rate and the manner of providing it should be clarified with the DLD and a local lawyer before building the financing plan.

What happens if you sell before the project is registered?

The sale is void. Article 11 of Resolution 6/2010 provides that an Off-plan sale made before the competent authorities approved the project and before it was registered with the DLD is "null and void". This is a critical point for an Israeli developer used to "pre-registration": in Dubai, down payments may not be collected before registration. When a broker markets the project, it too must be licensed and the marketing agreement must be registered with the DLD (Article 10), and it must deposit buyers' money directly into the Escrow account, without first deducting a commission (Article 12).

Is a permit needed to market the project in Israel?

Yes. Article 5 of Law 8/2007 requires the DLD's written approval before advertising or exhibiting an Off-plan sale, in local or foreign media. In practice, advertising permits are issued through the Trakheesi system, and the permit number appears in the advertisement. The DLD enforces the rule: in 2020 it announced fines on ten real estate companies and warnings to 30 more for breaches of the advertising requirements. Anyone marketing to Israeli buyers must also comply with Israeli law, as discussed in marketing a Dubai project to Israeli buyers.

What changed in the registration process in 2026?

On 3 September 2026 the DLD announced a platform called Initial Registration, which consolidates project registration, transaction registration and Escrow account management. According to the announcement, transactions that comply with the rules can be approved upon submission, several companies can be managed from one account with separate permissions for the submitter and the reviewer, and a consolidated view called Project 360 shows the status of units, Escrow accounts and financial data, with early alerts. For a foreign developer this is good news, but it does not replace the substantive requirements: the process is faster only when the documents are complete and in order.

What obligations apply to the developer once sales begin?

  • Start of construction: a developer that has not started construction within 6 months of approval of the Off-plan sale, without an acceptable reason, may be struck off the register (Article 17 of Law 8/2007).
  • Registering each sale in the interim register: late submission incurs a fine of AED 10,000 on the developer (Article 3 of Resolution 6/2010).
  • No collection beyond what is approved: the developer may not collect from buyers amounts beyond what the DLD has approved (Article 8).
  • Area: the net area governs. A shortfall of more than 5% requires compensation (Article 13).
  • Handover and registration: after the completion certificate, the developer may not delay handover or registration for a buyer who has met its obligations (Article 7).
  • Common property: a Building Management Statement approved by RERA before sale, under Article 20 of Law 6/2019.
  • Liability for defects: under Article 40 of Law 6/2019, the developer repairs defects in the structure of the common property for 10 years from the completion certificate, and defective installations for one year. The main contractor and the engineer are liable under the new Civil Code (Federal Decree-Law 25/2025, in force from 1.6.2026).

What are the sanctions on a developer that breaches the law?

Article 16 of Law 8/2007 provides for imprisonment and/or a fine of at least AED 100,000 for offences such as development without a licence, submitting false documents to obtain a licence, selling units in a fictitious project, misusing project funds and working with unregistered brokers. Alongside this, Article 17 allows a developer to be struck off the register if declared bankrupt, if its licence has been cancelled or if it did not start construction on time. At project level, RERA may cancel a project, which triggers the mechanism for refunding buyers from the Escrow account. See the developer's Escrow account obligations.

How does this fit with an Israeli developer's holding structure?

Most Israeli developers operate through a local project company, sometimes in partnership with a landowner or a local developer. In Dubai, a company is subject to corporate tax of 9% on profit above AED 375,000 (as of November 2026). In Israel, holding a foreign company requires reporting, including Form 150, and the risk of control and management from Israel should be examined. The tax treaty between Israel and the UAE was signed on 31 May 2021 and applies from tax year 2022. Details in taxation of an Israeli investor in a foreign project company and in structuring a JV agreement for an Israeli developer in Dubai.

Before you sign: how we assist an Israeli developer in Dubai

We assist Israeli developers in coordination with licensed local lawyers in Dubai: we build the company and partnership structure, map in advance all the approvals required before the first sale, prepare the Israeli documents through the full authentication chain (the UAE is not a party to the Apostille Convention), and coordinate the Israeli side of tax and reporting. As Ilan Leibovitch is also an active developer, we look at the timetable the way a developer looks at it: what is holding up sales and what can be prepared in parallel.

General information, not legal advice

This guide is general information current as of November 2026 and does not constitute legal or tax advice. Requirements and fees in Dubai change, and each project is examined on its own merits with a licensed local lawyer and an accountant in Israel.

Frequently asked questions

What is RERA developer registration?

It is the registration of a company in the register of real estate developers maintained by the DLD under Article 4 of Law 8/2007. A developer that is not registered and does not hold a licence from the competent authorities may not operate as a developer and sell Off-plan.

Can an Israeli developer register as a developer in Dubai?

We did not find an official restriction on Israelis as a group. The companies law allows full foreign ownership in most Mainland activities. However, a company with a foreign shareholder is restricted to areas designated for foreign ownership as regards land.

Can down payments be collected before the project is registered with the DLD?

No. Under Article 11 of Resolution 6/2010, an Off-plan sale before the project has been approved and registered with the DLD is void. All buyers' money is deposited into the project's Escrow account.

Is a permit needed to advertise a Dubai project in Israel?

Yes. Article 5 of Law 8/2007 requires the DLD's written approval before advertising or exhibiting, including abroad. In practice, the permits are issued through the Trakheesi system.

How long does a developer have to start construction after the sale is approved?

6 months. A developer that has not started construction within 6 months of approval of the Off-plan sale, without an acceptable reason, may be struck off the developer register under Article 17 of Law 8/2007.

What is the penalty for operating as a developer without registration?

Under Article 16 of Law 8/2007, imprisonment and/or a fine of at least AED 100,000. The same penalty also applies to false documents and to misuse of project funds.

How much does it cost to register as a developer in Dubai?

The registration fees are not published on a single official page, and commercial sources cite different amounts. As of November 2026, the current fee should be checked with the DLD before budgeting.

Read next · 9 min readUBO in Dubai: Ultimate Beneficial Owner Registration and Substance Obligations for an Israeli-Owned Emirati CompanyUBO registration in Dubai for an Israeli-owned company: who counts under Resolution 109/2023, deadlines, penalties, what remains of ESR and substance.Read the guide

Sources

  1. Dubai Legal Portal - Law No. 8 of 2007 Concerning Escrow Accounts for Real Estate Development
  2. Dubai Legal Portal - Executive Council Resolution No. 6 of 2010 (Implementing Bylaw of Law No. 13 of 2008)
  3. Dubai Land Department - Initial Registration platform for developers (3.9.2026)
  4. Dubai Media Office - DLD fines real estate companies for advertising violations (2020)
  5. u.ae - Full foreign ownership of commercial companies
  6. Afridi & Angell - Law No. 6 of 2019 on Jointly Owned Property

Let’s start with a conversation.

A sound international transaction begins long before signing. A short introductory call will clarify whether, and how, we are the right firm to support you.

Not ready for a call yet? Deal readiness check · Get the monthly newsletter

Office
7 Hanafat HaDegel St., Ness Ziona, Israel
Romania
Meetings in Bucharest by prior arrangement
  • Hebrew · Romanian · English
  • Ness Ziona · Bucharest meetings by appointment
  • Online meetings