In brief
When buying a new home from a developer in Romania, five key documents pass through your hands: the land book extract, the preliminary contract, the building permit, the works acceptance report and the final contract of sale. They are all in Romanian, but you do not need to know Romanian to check them. You need to know where to look, and to make sure that the land book number, the cadastral number, the developer's identity and the permit number are identical in all the documents.
Key takeaways
- 1The extract is built of three parts: A the property description, B the owners and documents, C the encumbrances. "NU SUNT" in Part C means there is no entry.
- 2A preliminary contract for a home not yet built is signed only before a notary, and only after the building permit has been registered in the land book (Law 169/2026, Article 422(7)).
- 3From 26 August 2026 permits are issued on a new official form under Order 975/2026 of the Ministry of Development, so an older permit will look different.
- 4Construction not in accordance with the permit cannot pass acceptance (Law 169/2026, Article 280). Where there are remediable defects, the committee suspends the acceptance and allows up to 90 days.
- 5A contract transferring ownership of immovable property must be notarial, otherwise it is void (Civil Code, Article 1244).
Israeli buyers receive a pile of documents in Romanian from the Romanian developer, and often sign on the basis of a partial translation or an oral explanation. This guide explains, document by document, which fields determine almost everything, what to check in each, and what should make you stop and ask.
The principle linking all the documents is simple: the same numbers must recur in all of them. The land book number, the cadastral number, the company name and the permit number. When one number does not match, that is the time to ask your lawyer.
What do you check in the land book extract (Extras de carte funciară)?
The extract for information (extras pentru informare) is the first and cheapest document to request. Anyone can order it by the property number. It shows who owns the property and what is registered against it.
| Part of the extract | What to check | Stop sign |
|---|---|---|
| Header: office, application number and verification code | That the code works on the ANCPI verification website. According to the wording on the extract, the code is valid for 30 days | An extract without a code, a screenshot or an edited file |
| Land book number (Carte Funciară Nr.) | That it is the number in the contract. Only one property is registered on one land book sheet (Civil Code, Article 878) | An extract for the whole plot without an extract for your future unit |
| Part A: property description | That the area and the cadastral number match the contract and the site. Intravilan means within the built-up area | Extravilan on a plot presented as a building plot, or a discrepancy in area |
| Buildings (Construcții) | For an existing home, that the building is registered (for example 00000-C1). For a new home the list may be empty until construction is completed | A home that has stood for years and is not registered |
| Part B: owners and documents | That the registered owner is the seller, and that all the owners sign | Provisional registration instead of final registration, an owner who is not the seller, notations of proceedings |
| Part C: encumbrances (SARCINI) | That the part is empty, or that every entry has a written removal plan before payment | A mortgage without a release letter, an attachment, a prohibition on sale and encumbrance, or another buyer's preliminary contract |
| Annex 1: technical details | That the land use is suitable for housing, and for buildings "Cu acte" (with documents) | Agricultural use on a building plot, or a building without "Cu acte" |
Under the Civil Code (Article 881) there are three types of entry: intabulare (final registration), înscriere provizorie (provisional registration) and notare (notation). In Part B you want to see a final registration of the seller.
The extract reflects the situation on the day and at the time it was issued. Order a new extract before every significant payment. On the day of signing the notary orders a different extract, the "extract for authentication" (extras pentru autentificare), which is valid for 10 working days, during which the registration office registers nothing else against the property (Law 7/1996, Article 35).
A preliminary contract for a home not yet built is signed only before a notary, and only after the building permit has been registered in the land book (Law 169/2026, Article 422(7)).
What must appear in the preliminary contract (Promisiune bilaterală de vânzare-cumpărare)?
A preliminary contract has no official form, but the law provides that it must include all the clauses without which the final contract cannot be performed (Civil Code, Article 1279). When buying from a developer a home that has not yet been built, it is signed only before a notary, and only after the building permit has been registered in the land book and an extract has been opened for the future unit (Law 169/2026, Article 422(6) to (7)).
- Name of the document: a "Promisiune bilaterală" is a mutual undertaking to sell and to buy. Make sure it is not a convenție de rezervare (reservation agreement), which is a different stage with different rules. A document called a "letter of intent" that collects a significant sum is a stop sign.
- The parties: the company name, its registration number (CUI) and who signs on its behalf. The company must be the one registered as owner in Part B of the extract. If you sign through an attorney, the power of attorney must be complete and certified.
- The property: "Locuința individuală viitoare" means the future home. The land book number and cadastral number of the unit are required, identical to the extract. A general description such as "a villa in the project" is not enough.
- The building permit: number and date, which also appear in the extract. "The permit is on its way" means that you cannot sign.
- Price and payments: currency, whether VAT is included, and payments by construction stage. Most of the price up front before the structural frame stands is a warning sign.
- The account: under Article 422(10), a separate account of the developer, dedicated to the project. An account of a private individual or of another company is a stop sign.
- Arvună or avans: with a "confirmatory" earnest payment (arvună confirmatorie), if the buyer defaults the seller keeps the sum, and if the seller defaults the buyer may claim double (Article 1544). If the contract says nothing, a sum paid under a preliminary contract is deemed an advance on account of the price (Article 1670).
- Date of the final contract: a clear date or a clear event. If a party refuses to sign without justification, the other party may seek a judgment replacing the contract within 6 months (Article 1669). "On the date the developer determines" is not a date.
- Handover and compensation: a handover date, compensation for each day of delay, and what happens in the event of a long delay.
- Seller's representations: on encumbrances, claims and debts, consistent with Part C of the extract.
- Registration: the notary applies to register the contract on the day of signing or on the next working day (Article 422(8)). A request "not to register for now" is a stop sign.
- Annexes: technical specification, finishing level and plans, signed and attached.

How do you tell whether the building permit (Autorizație de construire) is in order and valid?
From 25 August 2026 the Planning and Construction Code, Law 169/2026, applies, and from 26 August 2026 new permits are issued on a new official form, "F_A_04", under Order 975/2026 of the Ministry of Development. A permit issued before then was written on the old form and will look different.
| Field in the permit | What to check | Stop sign |
|---|---|---|
| Number, date and authority | That the authority is the town hall or council of the plot's location, and that the number appears in the contract and in the extract | A number that does not appear in any other document |
| References | The permit refers to the urban planning certificate (certificat de urbanism), which is an information document only | An urban planning certificate presented as "approval to build" |
| The applicant and what is permitted | That the company is identical to the owner in the extract and to the seller in the contract, and that the number of units and storeys matches | More storeys or units in the marketing brochure than in the permit |
| The property | Land book number and cadastral number identical to the extract | A permit for another plot or for a plot before division |
| Value of the works | Only that it appears. It is a basis for fees, not the price of the home | No particular sign |
| The design (P.A.C.) | The name of the registered architect (TNA) and their registration number | No architect details |
| Validity and execution period | The date of issue, and that a notice of commencement of works was filed | A permit more than 3 years old without such a notice |
| The stamped plans | The plans bear the stamp "vizat spre neschimbare" (approved, not to be changed). Compare storeys and areas | "The plans cannot be shown" |
| Obligations of the permit holder and signatures | A sign on site, all the signatures, and if there is an extension, until when | A site without a sign, a missing signature, an expired extension |
Under Article 309 of Law 169/2026, a permit has 3 years from the date of issue for construction to begin, and after a notice of commencement of works its validity continues for the whole execution period. The form allows one suspension of up to 12 months, as well as a request for extension at least 15 days before expiry, for up to 12 months. Building not in accordance with the stamped plans is an offence or a contravention under Articles 356 and 357 of the law.
What is the difference between an acceptance report and a handover report?
The works acceptance report (Proces-verbal de recepție la terminarea lucrărilor) establishes that construction has been completed and was built in accordance with the permit. It is drawn up between the developer, the "investor" in the language of the regulations, and the contractor, in a committee that includes a representative of the authority that issued the permit. The handover report (proces-verbal de predare-primire) is signed between you and the developer on the day you receive the keys, and has no official form. Under Article 422(5)(k), the developer hands over the home only after the acceptance has been approved and there are permanent utility connections.
Under Law 169/2026 (Article 280), construction is considered complete only after acceptance of the works, and construction not in accordance with the permit cannot pass acceptance. The regulations on acceptance of buildings, Government Decision 273/1994, remain in force (Article 577(6)). What to check in the report:
- The developer's approval: at the top of the report "ADMITEREA" (acceptance) is marked and not "RESPINGEREA" (rejection), with a signature, within 3 days of the committee's decision (Regulation 19).
- Date: the day of acceptance is the day the developer signs, and the contractor's warranty period starts from it (Regulation 20). A "PROCES-VERBAL DE RECEPȚIE PARȚIALĂ" is a partial acceptance of a stage, not completion of construction.
- The property and the permit: address, cadastral number and land book number identical, and the same permit you saw, valid.
- The committee: the developer's representative as chair, a representative of the authority that issued the permit, and 1 to 3 experts who were not involved in the design or construction (Regulation 11). In a dispute, the opinion of the authority's representative prevails (Regulation 16). The absence of a town hall representative is a stop sign.
- The secretariat: an authorised site supervisor (diriginte de șantier) prepares the documents. They are not a member of the committee.
- Findings: sections 6.2 to 6.4 refer to three lists: defects not remedied, fire safety measures not carried out, and defects that cannot be remedied. The lists should be empty.
- Warranty: the warranty period is stated. Separately, the contractors are liable for 10 years for hidden defects and for the entire life of the building for structural defects resulting from non-compliance with the design or the standards (Law 169/2026, Article 451).
- The decision: where there are remediable defects, the committee suspends the process in a separate report and allows up to 90 days for remedy (Regulation 17). A building whose acceptance was rejected may not be used until the remedy (Regulation 22(3)).
On acceptance of the works the supervisor hands over to the owner the building's technical book (cartea tehnică) and the maintenance manual (Law 169/2026, Article 528), and the developer sends the acceptance report to the owner within 5 days of completion of the acceptance (Regulation 23). Ask for both.
What do you check in the final contract of sale (Contract de vânzare-cumpărare)?
This is the document by which ownership passes to you. A contract transferring ownership of immovable property must be made in a notarial document, otherwise it is void (Civil Code, Article 1244). When buying from a developer it is signed after acceptance of the works and before taking possession. It has no official form, and the notary drafts it.
- Title and notary: "Contract de vânzare-cumpărare" and no longer "Promisiune", signed before a notary.
- Parties: the seller is the owner in Part B and the same company that signed the preliminary contract, and your name is written exactly as in your passport. An attorney needs a special notarial power of attorney, and the notary checks in the national register that it has not been revoked (Law 36/1995, Article 91(2)).
- The property: a notarial document transferring ownership is signed only for a property registered in the land book, save for exceptions (Law 7/1996, Article 36(1)). The building is registered on the basis of the authority's confirmation that construction was carried out in accordance with the permit and that there is an acceptance report (Article 37(1)). Make sure the building appears in the extract.
- Extract for authentication: its number and date appear in the contract. A new encumbrance that was not in the extract you checked is a stop sign.
- Price: identical to the preliminary contract, the advance payments stated and set off, and the balance and its due date clear.
- Handover: handover means placing the property at your disposal with everything needed to possess it (Civil Code, Article 1685). Make sure there is a date and a signed handover report.
- Seller's liability: to transfer ownership, to hand over the property, and to protect against the rights of others (evicțiune) and against defects (Article 1672).
- Expenses: unless the contract provides otherwise, the expenses of drawing up the contract of sale are borne by the buyer (Article 1666(1)). Make sure it is written who pays the notary and the fees.
- Registration: the notary must apply for registration on their own initiative, on the day of signing or on the next working day (Law 7/1996, Article 35(1)). After a few days, obtain an extract in which you are registered in Part B with final registration.
- Interpreter: if you do not understand Romanian, an interpreter authorised by the Romanian Ministry of Justice takes part and signs together with the notary (Law 36/1995, Article 82(2)).
- The notary's certification: an încheiere de autentificare with a number and date and the words "Se declară autentic prezentul înscris" (Article 99). The original is kept in the notary's archive, and you receive a counterpart (duplicat) with the same evidential force (Article 98).
How do you cross-check the documents against each other?
Four documents answer four questions: who owns the property and what is registered against it (the extract), what you committed to (the preliminary contract), what may be built (the permit), and whether that is what was built (the acceptance report). The final contract closes the circle, and the same numbers must appear in it again. The comparison between the permit and what was actually built is not a technical detail: construction not in accordance with the permit cannot pass acceptance, and that is the difference between a home that can be registered and sold and a home that cannot.
What to do before every signature, and how we accompany the check
Ask every developer for all the documents, and pass them to an independent Romanian lawyer who represents only you. The developer's lawyer represents the developer. We help Israeli buyers go through the documents field by field, understand the terms and prepare a list of questions for the lawyer and the notary. Signatures and registration take place before a notary licensed in Romania.
The above is general information and is not legal advice. The rules are based on the text of the legislation and the forms as presented in the source, as at October 2026. Forms and texts may change, and a document issued before 26 August 2026 may look different. The actual documents must be read by an independent lawyer.
Frequently asked questions
What is the difference between an extract for information and an extract for authentication?
Anyone can order an extract for information, and it is used to check a property. An extract for authentication is ordered by the notary ahead of signing. It is valid for 10 working days, during which the registration office registers nothing else against the property (Law 7/1996, Article 35).
Must a preliminary contract for a home not yet built be signed before a notary?
Yes. Under Article 422(7) of Law 169/2026 it is signed only before a notary, after the building permit has been registered in the land book and there is an extract for the future unit. The notary applies to register it on the day of signing or on the next working day.
How do you know whether the building permit is still valid?
Check the date of issue and whether a notice of commencement of works was filed. The permit is valid for 3 years for construction to begin, and after the notice its validity continues for the execution period. At the end of the form there is space for an extension, if granted.
What is the difference between the acceptance report and the handover report?
The acceptance report establishes that the building was built in accordance with the permit and is signed by a committee that includes a representative of the authority. The handover report is signed between you and the developer on the day you receive the keys, and comes only after the acceptance has been approved.
When is the final contract signed in a purchase from a developer?
After acceptance of the works and before taking possession. The contract must be notarial, and the notary sends the registration application on the day of signing or on the next working day.
Read next · 7 min readA Will for an Israeli With Property in Romania: Choice of Law, Form of the Will and Coordination With the Will in IsraelHow to write a will that works for property in Romania: Regulation 650/2012 and choice of law, notarial or handwritten wills, reserved shares, the Israeli will.Read the guideSources
- Legea 169/2026 - Codul amenajării teritoriului, urbanismului și construcțiilor (Monitorul Oficial nr. 661, 10.08.2026)
- Codul civil, formă consolidată (legislatie.just.ro)
- Legea 7/1996 a cadastrului și a publicității imobiliare (legislatie.just.ro)
- Legea 36/1995 a notarilor publici (legislatie.just.ro)
- HG 273/1994 - Regulamentul de recepție a construcțiilor (e-guvernare.ro)
- ANCPI - Agenția Națională de Cadastru și Publicitate Imobiliară
The information in this guide is general in nature and does not constitute legal or tax advice on any specific transaction. Every transaction is assessed on its own facts.