Ilan Leibovitch & Co.Lawyer and real estate developer
RomaniaRegulation

Building or Buying Near a Nature Reserve or Natura 2000 Site in Romania: Which Approvals Are Required and How to Check a Plot

A plot near a lake, forest or Natura 2000 site in Romania: when an environmental permit is needed, who approves, and what to check before paying a deposit.

By Adv. Ilan LeibovitchUpdated: 8 min read
RegulationPl. I

In brief

A protected area in Romania is not a blanket ban on building, but it adds a layer of approvals. Under the new planning code, Law 169/2026, a detached house is generally exempt from an environmental permit unless it is inside a protected natural area or reserve, in which case the approval of the area's administrator and a procedure before the environmental authority are also required. What decides the matter is exactly where the boundary of the protected area runs in relation to the plot, and this is checked on the official maps and in the urban planning certificate before you pay.

Key takeaways

  1. 1Under Article 268(2)(a) of Law 169/2026, a detached house does not need an environmental permit, except for a house inside a protected natural area or a reserve.
  2. 2Inside a protected natural area, plans and building projects need the approval of the area's administrator (Article 197(2)), and the land use there may not be changed (Article 197(4)).
  3. 3The urban planning certificate (certificat de urbanism) lists which approvals are required for a specific plot, including the opinion of the environmental authority and the water management approval (Article 266).
  4. 4In protected zones, a PUZ may increase building rights by no more than 10%, and only once (Article 66(1)(f)).
  5. 5Private land can also lie inside a Natura 2000 site, so check the plot itself and do not rely on the name of the area.

An open view of a forest or a lake is one of the reasons Israelis look for a plot or a house outside the city in Romania. But many of Romania's forests, lakes and wetlands are protected by law, some as part of the European Union's Natura 2000 network and some as national protected areas. A buyer who does not check may discover that entirely different rules apply to their plot than to the neighbours' plots.

This guide deals with the legal and planning side of nature protection: what the law permits and what it adds, who must approve, and how to check a plot before committing. The rules are presented as they stand as of October 2026, under the new Planning and Construction Code.

Is it permitted to build a house inside a Natura 2000 site in Romania?

Not freely, but it is not always prohibited either. Protection does not mean “no building in the area”. It means that every plan or project inside the protected area undergoes an additional review, and that a project that does not fit the area's protection regime will not be approved.

Law 169/2026, the Code of Spatial Planning, Urbanism and Construction, entered into force on 25 August 2026 and treats protected natural areas as protected zones. It does not replace environmental legislation. The management of these areas and interventions in them are governed by Emergency Ordinance 57/2007 (OUG 57/2007) and by Law 95/2016, which established the National Agency for Protected Natural Areas, ANANP. In other words, two sets of rules apply in parallel, and both must say “yes”.

The key point

The question is not whether the area is “green” or “near a reserve”. The question is whether the line of the protected area crosses the plot. A plot lying one metre outside the boundary is subject to the ordinary local rules, and a plot inside it is subject to a full environmental procedure.

Inside a protected natural area, plans and building projects need the approval of the area's administrator (Article 197(2)), and the land use there may not be changed (Article 197(4)).

Key takeaways

What actually changes when the plot is inside a protected area?

The new code spreads the rules across several articles. These are the ones relevant to a buyer or builder of a private house:

SubjectWhat the code providesArticle of Law 169/2026
Environmental permit for a detached houseGenerally not required, unless the house is inside a protected natural area or a reserve268(2)(a)
Approval of the area's administratorPlans and building projects inside a protected natural area need its approval at every stage197(2)
Land useLand use may not be changed inside a protected area, and projects that do not fit the protection regime are prohibited197(4)
Prior approval for worksWorks on properties in protected zones require prior approval, and for natural assets, from the environmental authority189(6), 190(1)
Documents for Natura 2000A property in a Natura 2000 site requires supplementary documents under the dedicated legislation265(6)
Increase of building rights through a PUZUp to 10% in protected zones, once66(1)(f)
Appearance in plansProtected natural areas must appear in the planning documents188(2)

The PUZ row in the table matters for anyone hoping that “more will be approved in the future”. In a PUZ (detailed zonal plan) in a protected zone, the ceiling on increasing building rights is lower than the one that applies in an ordinary zone. A plot inside a protected area is not expected to become a plot for dense construction.

Bucharest

Who approves what: the environmental authority, the area administrator and the municipality

  • The local authority (primărie) issues the urban planning certificate and the building permit. It does not decide on its own whether the project fits nature protection.
  • The county environmental protection agency (APM), which is the local branch of the Environmental Protection Agency, runs the environmental procedure under Law 292/2018 on environmental impact assessment and under Ordinance 57/2007. In the Ilfov area, for example, this is APM Ilfov.
  • The administrator of the protected area gives the approval the code requires for plans and projects inside the area. ANANP publishes information on the protected areas and on the bodies that manage them.

Inside a Natura 2000 site, it is the environmental authority that decides whether the project also needs an appropriate assessment (evaluare adecvată), meaning a dedicated review of the impact on the site. It is impossible to know in advance what the answer will be in every case. That is exactly why you ask before the purchase and not after it.

Inside the boundary, on the boundary or nearby: what is the difference?

Location of the plotWhat usually appliesThe question to clarify
Inside the protected areaAn environmental procedure, approval of the area's administrator, and a possible prohibition on new construction or on a change of land useIs building permitted here at all, and what did the area administrator and the environmental authority say?
Close to the boundary, outside itThe ordinary local rules, but the urban planning certificate may require an environmental opinionWhich approvals are listed in the urban planning certificate?
Near a lake or streamWater management rules as well: the bank, a protection strip, flood risk, and also the local planWhere exactly does the line between the plot and the body of water run?

Another point that surprises buyers: a protected area is not necessarily state land. In the official data form of one of the Natura 2000 sites north of Bucharest, for example, 21% of the area is registered as privately owned. A private plot with a clean land register extract can be inside a protected site, and the extract alone will not reveal this to you.

What must appear in the permit file for a house in a protected zone?

The document that determines the list of approvals for a specific plot is the urban planning certificate. Under Article 266(1) of the code, it sets out the approvals required for the building permit, and depending on the location these include the opinion of the environmental authority and the water management approval (aviz de gospodărire a apelor), under Article 266(2)(f) and (h).

In a developer's project, or for a house you plan to build yourself, the complete file should include at least:

  1. An up-to-date urban planning certificate, with the list of approvals it requires.
  2. The decision of the environmental authority: an environmental permit, or a document stating that no such procedure is required.
  3. In a Natura 2000 site, the supplementary documents under Article 265(6), and where necessary the results of the appropriate assessment.
  4. The approval of the protected area's administrator, when the plot is inside the area.
  5. The water management approval, when the plot is close to a body of water.
  6. The building permit itself, which is issued after all these approvals.
Warning sign

A building permit issued for a plot inside a protected area, where the file does not show the position of the environmental authority and of the area administrator, calls for clarification. Do not accept an oral explanation in place of the document.

How do you check a plot before paying a deposit?

  1. Compare the plot with the Natura 2000 map. The European Environment Agency (EEA) publishes an online map with the boundaries of the sites. Compare it with the plot's survey plan, not just with the address.
  2. Also check national protected areas. Not every reserve in Romania is a Natura 2000 site. ANANP publishes information on the national areas and on who manages them.
  3. Request an urban planning certificate for information. Under Article 254 of the code, any person may request one, even for a plot they do not own. It shows the land use, the building rights and the required approvals.
  4. Read the PUG. The general urban plan of the locality must mark protected natural areas (Article 188(2)).
  5. Ask the environmental authority in writing. If the plot is inside a protected area, request a written answer on the procedure that will apply, before any payment.
  6. For an existing project, request the file from the developer. The urban planning certificate, the environmental decision and the building permit, and compare them with one another.

We covered the urban planning certificate, the PUZ and reading a building permit in more detail in separate guides on planning and construction and on checking a permit before buying. We wrote about additions such as a pool, a pergola and a fence in the villa additions guide. Keep in mind that in a protected zone even a small addition, such as an extension or a jetty, may require more approvals than in an ordinary neighbourhood.

What should be written in the purchase contract?

  • A declaration by the seller as to whether they know the plot is inside or close to a protected area, and which approvals have already been obtained.
  • When buying a plot in order to build on it, completion of the transaction can be made conditional on receiving a written answer from the environmental authority or on obtaining the required approvals.
  • A list of the documents the seller or developer hands over, as an annex to the contract.
  • In a new project, an undertaking that the construction was carried out in accordance with the attached environmental decision and permit.

Is nature protection only a restriction?

Not necessarily. A protected forest or lake is a neighbour that will not turn into a block of buildings. The view and the quiet are protected by law, not just by an agent's promise. On the other hand, a buyer inside the boundary must accept that their own plans will also undergo a stricter review. The right decision depends on what you plan to do with the plot.

What should you do before signing?

Before an agreement, and certainly before a deposit, you should have in hand the plot's survey plan set against the map of protected areas, an urban planning certificate for information, and, if the plot is inside the boundary, a written answer from the environmental authority. We accompany Israeli buyers and developers through this review together with licensed lawyers, notaries and architects in Romania. Applications to the authorities, checks in the land register and the signing of the contract are carried out by locally licensed professionals.

General information

This article is general information, current as of October 2026, and is not legal advice for a specific case. The boundaries of protected areas and the environmental procedures are determined by the competent authorities, and the new planning code and its implementing regulations are still being updated. Before a purchase, check the specific plot with the local authority and the environmental authority.

Frequently asked questions

Does a detached house near a nature reserve in Romania need an environmental permit?

A detached house outside a protected natural area and outside a reserve generally does not need a separate environmental permit (Article 268(2)(a) of Law 169/2026). However, the plot's urban planning certificate may require an environmental opinion, so read it.

Can you build a house inside a Natura 2000 site in Romania?

Not freely. Inside a protected area, an environmental procedure and the approval of the area's administrator are required, and projects that do not fit the protection regime are prohibited. Whether building is permitted on a specific plot is decided case by case.

How do you know whether a plot in Romania is in a protected area?

Compare the plot's survey plan with the Natura 2000 map of the European Environment Agency and with ANANP's information on national areas, and request an urban planning certificate for information from the local authority. If the plot is inside the boundary, ask the county environmental protection agency in writing.

Who manages protected areas in Romania?

The National Agency for Protected Natural Areas, ANANP, established by Law 95/2016, together with the environmental authorities. The environmental procedure for a specific project is conducted with the county branch of the Environmental Protection Agency.

Can a PUZ increase building rights in a protected zone?

Only to a limited extent. Under Article 66(1)(f) of Law 169/2026, in protected zones a PUZ may increase building rights by no more than 10%, and only once.

Read next · 7 min readA Will for an Israeli With Property in Romania: Choice of Law, Form of the Will and Coordination With the Will in IsraelHow to write a will that works for property in Romania: Regulation 650/2012 and choice of law, notarial or handwritten wills, reserved shares, the Israeli will.Read the guide

Sources

  1. Legislation portal of the Romanian Ministry of Justice (legislatie.just.ro)
  2. Romanian National Agency for Protected Natural Areas (ANANP)
  3. Romanian National Environmental Protection Agency (ANPM)
  4. Natura 2000 map of the European Environment Agency (EEA)
  5. European Commission: the Natura 2000 network

The information in this guide is general in nature and does not constitute legal or tax advice on any specific transaction. Every transaction is assessed on its own facts.

Let’s start with a conversation.

A sound international transaction begins long before signing. A short introductory call will clarify whether, and how, we are the right firm to support you.